Centralised Production & Advanced Planning for Dynamics 365 Business Central User Guide
Introduction
This guide explains how to set up Centralised Production Planning (CPP) and Advanced Planning in Microsoft Dynamics 365 Business Central, and how to plan with the group planning board. This will cover every setup page and every field: what it does, its default, and what to enter. We also provide a section that shows planners how to use the board: change a date, see the effect on every linked order, apply the change and check capacity.
To get the app, visit the Microsoft Marketplace — d365 Centralised Production Planning for Business Central
NOTE: This document is the V2 (version 2) of the original Centralised Production Planning app user guide. New features and updates are included that improves upon the application.
What The Apps Do
| App | What it adds | Used in |
|---|---|---|
| Centralised Production Planning | Stock and capacity of every production company on the planning worksheet; sourcing of planning lines from a production company through intercompany. | Every company of the group |
| Advanced Planning | Group planning board (Gantt) with pegging and impact, Chain Planning across companies, supply chain trace, shared machines, capacity load and lot advice. | Every company of the group |
| MDS Connector | Optional. Requests missing items, BOMs and routings from the master company. | Companies that use MDS Master Data Sync |
| Production Planning Board | The same planning board for a single company, without anything that spans companies. | One company |
Conventions
| You see | Meaning |
|---|---|
| Bold text | A page, field or action as it appears in Business Central. |
| Choose the Search (Tell me) icon | Use Tell me (Alt+Q) to search for the page. |
| 3 | A numbered callout. The same number marks the field on the screenshot and in the field table below it. |
| REQUIRED | The apps do not work without a value in this field. |
Before You Start
Your administrator installs the apps and grants you access. You need a user who can open every company of the group. Set the companies up in the order on the next page.
How The Setup Fits Together
The apps plan supply along a chain of companies, connected by intercompany orders. Setup has three layers: standard Business Central in every company, CPP in the companies that plan, and Advanced Planning for the group.
Company Roles
| Level | Role (example) | What it does |
|---|---|---|
| 1 | Sales company (SALES CO) | Takes customer orders; buys from the plant through IC purchase orders. |
| 2 | Production company (MAT PLANT) | Receives IC sales orders, produces, buys components — also from level 3. |
| 3 | Production company (CARPET PLANT) | Supplies level 2, usually make-to-stock in lots. |
Setup Order
Work in this order; each step depends on the one before. Once (shared) pages hold one set of data for all companies.
| # | Step | Companies | Why |
|---|---|---|---|
| 1 | Get access and set your role | All | You can open every page of this guide. |
| 2 | Intercompany Setup and IC Partners | All | Intercompany orders carry demand from one company to the next. |
| 3 | IC vendors and customers | All | Purchase orders go to a vendor; sales orders come from a customer. |
| 4 | Items in every company | All | Same item numbers; replenishment system per role. |
| 5 | Work centers, machine centers, calendars | Production | Production orders and capacity load need calendars. |
| 6 | Manufacturing Setup and planning worksheet | All | Planning parameters and the worksheet batch Chain Planning uses. |
| 7 | Company Information | Production | Marks the plants so planning companies find them. |
| 8 | CPP Setup and production companies | Planning | Which plants a company sources from, through which IC vendor. |
| 9 | Advanced Planning Setup | All | Board defaults and Chain Planning in each company. |
| 10 | Planning Group, Shared Machines, Board Views | Once (shared) | Which companies plan together and how the board looks. |
| 11 | Verify the setup | Planning | Readiness check, a chain run and the board. |
Access & Role Center
Your administrator installs the apps once for the whole group. Before you start, check that you have the right access and the planner’s home page.
Access You Need
| Permission set | Who needs it |
|---|---|
| Centralised Prod. Planning - User | Planners. Planners also need read access in every production company, to see items, BOMs and stock there. |
| Centralised Prod. Planning - Admin | Whoever maintains the planning setup and the list of production companies. |
| d365 Advanced Planning | Planners and key users who use the planning board, Chain Planning and the shared setup. |
| Centralised Prod. Planning - MDS Connector | Users who request missing items, BOMs or routings from the master company. |
Important: Chain Planning and Apply Changes on the planning board update orders in the other companies for you. You therefore need planning, sales, purchase and production access in every company of the group.
Set Your Role
-
Choose the Search (Tell me) icon, enter My Settings, and then choose the related link.
-
In Role, choose Production Planner (Group), and then choose OK.
Your home page now shows planning, the planning board, Chain Planning and every setup page of this guide.

The home page: 1 planning board, 2 Chain Planning, 3 and 4 the setup pages.
Part A - Business Central Prerequisites
This is the Standard Business Central setup that the apps rely on. If intercompany, items and capacity already work in your companies, check the fields marked as important for the apps and move on.
Set Up Intercompany in Every Company
Demand travels down the chain as intercompany orders: a purchase order in the buying company arrives as a sales order in the selling company. That only works when every company has its own intercompany identity.
To set up intercompany:
-
In each company, choose the Search (Tell me) icon, enter Intercompany Setup, and then choose the related link.
-
Fill in the fields as described in the table.
-
Repeat in every company of the group.

Intercompany Setup
| Field | Description | Default | |
|---|---|---|---|
| 1 | IC Partner Code REQUIRED | The code that identifies this company to its partners. Every other company uses this code in its IC partner list. Use a short, stable code per company. | |
| 2 | IC Inbox Type REQUIRED | How transactions reach this company. Choose Database: all companies are in the same environment, so intercompany documents are delivered directly to the inbox. | File Location |
| 3 | IC Inbox Details REQUIRED | With Database, the name of this company. | |
| 4 | Auto. Send Transactions | Sends intercompany documents as soon as they are released or posted, without a stop in the outbox. Recommended: On. Chain Planning also sends new IC purchase orders itself when Send IC Orders Automatically. | Off |
Note: The page can show more fields, such as a default IC journal template and batch. You don’t need them for planning.
Set Up IC Partners
In every company, create an IC partner for each neighbour in the chain: level 1 needs level 2; level 2 needs levels 1 and 3; level 3 needs level 2.
-
Choose the Search (Tell me) icon, enter Intercompany Partners, and then choose New.
-
Fill in the fields, then repeat for the next partner.

Intercompany Partner Card
| Field | Description | Default | |
|---|---|---|---|
| General | |||
| 1 | Code REQUIRED | The partner company’s IC Partner Code from its own Intercompany Setup. Must match exactly. | |
| 2 | Name | Free text. | |
| 3 | Data Exchange Type | Choose Database when both companies are in the same environment. | Database |
| 4 | Inbox Type REQUIRED | Must be Database so documents go straight into the partner’s inbox. | |
| 5 | Inbox Details REQUIRED | The partner’s company name. | |
| 6 | Auto. Accept Transactions | Accepts incoming documents from this partner automatically. Chain Planning also accepts the IC inbox as its first step, so either works. Recommended: On. | Off |
| Sales & Purchase Transactions | |||
| 7 | Customer No. | The customer in this company that represents the partner when it buys from you. Needed on partners that buy from this company. | |
| 8 | Receivables Account | G/L account for intercompany receivables. Needed to post. | |
| 9 | Vendor No. | The vendor in this company that represents the partner when you buy from it. Needed on partners that supply this company. | |
| 10 | Payables Account | G/L account for intercompany payables. | |
| 11 | Outbound Purch. Item No. Type | Which item number is sent on purchase documents. Internal No. works because item numbers are the same in every company. Use Common Item No. or Item Reference only if they differ. | Internal No. |
Set Up IC Vendors, Customers & Item Numbers
Every link in the chain needs a vendor on the buying side and a customer on the selling side, both with the partner’s IC Partner Code.
| Company | Vendor (buys from) | Customer (sells to) |
|---|---|---|
| Level 1 — sales company | V-IC-MATS → IC partner of level 2 | — (external customers) |
| Level 2 — mat plant | V-IC-CARPET → IC partner of level 3 | C-IC-SALES → IC partner of level 1 |
| Level 3 — carpet plant | — (external suppliers) | C-IC-MATS → IC partner of level 2 |
To set up the vendor and the customer:
-
Open the Vendor Card (or create a vendor). On the General FastTab, set IC Partner Code.
-
Fill in the usual posting groups, payment terms and so on, as for any vendor.
-
Open the Customer Card in the selling company and set IC Partner Code the same way.

Vendor Card: 1 IC Partner Code. The customer card has the same field.
| Field | Description | |
|---|---|---|
| 1 | IC Partner Code (vendor) REQUIRED | On the vendor that represents a production company. Purchase orders to this vendor are sent through intercompany. CPP uses this vendor as the IC Vendor No. of the production company. |
| 2 | IC Partner Code (customer) REQUIRED | On the customer that represents a buying company. Incoming IC sales orders are created for this customer. |
Item Numbers
The apps find an item in another company by its number. Use the same item number, base unit of measure and item tracking code in every company that handles the item. With the MDS Connector, MDS keeps them in step.
Caution: If MDS or another tool copies items between companies, exclude the planning fields of the next page (Replenishment System, Vendor No., Manufacturing Policy, Routing No., Production BOM No.). They differ per company on purpose.
Set Up Items in Every Company
The same item plays a different role in each company: bought in the sales company, produced in the plant. The item card fields below decide what planning suggests in each company.

Item Card
| Field | Sales company (level 1) | Production company | Why | |
|---|---|---|---|---|
| 1 | Replenishment System | Purchase | Prod. Order | Purchase makes planning suggest a purchase; CPP turns it into an IC purchase from the plant. |
| 2 | Vendor No. | IC vendor of the plant | Blank (or the IC vendor of the next level for bought components) | Default vendor of the planning line. CPP can change it per line. |
| 3 | Lead Time Calculation | Plant lead time, e.g. 2D | Blank | Planning dates the purchase this many days before the need. |
| 4 | Manufacturing Policy | — | Make-to-Order for mats; Make-to-Stock for carpet | Make-to-Order links the production order to the IC sales order: the board pegs and traces it. |
| 5, 6 | Routing No., Production BOM No. | Blank | Certified routing and BOM | Production orders, operations on the board and capacity load. |
| 7 | Reordering Policy | Order or Lot-for-Lot | Order (MTO) or Lot-for-Lot | Without a policy the item is not planned. |
| 8 | Include Inventory | On | On | Planning uses stock before it suggests new supply. |
| 9 | Safety Lead Time | Optional | Optional | Buffer days; shows as slack on the board. |
| 10 | Item Tracking Code | Same in every company | Same in every company | Lot advice needs lot tracking. Keep the base unit of measure the same everywhere too. |
Set Up Work Centers, Machine Centers & Calendars
Only production companies need capacity. Production orders schedule their operations on machine centers; the planning board compares the load of those operations with the calendar.
-
Choose the Search (Tell me) icon, enter Work Centers, and create a work center per production line.
-
Enter Machine Centers and create a machine center per machine, with Work Center No. of its line.
-
On each card choose Calculate Calendar, from today to at least the plan horizon (90 days by default).
-
Use the machine centers in the routings of the produced items, and certify the routings.

Work Center Card
| Field | Description | Default | |
|---|---|---|---|
| 1 | Work Center Group Code REQUIRED | Groups work centers for reporting. Business Central requires it before a calendar can be calculated. | |
| 2 | Unit of Measure Code | Time unit of capacity and run times. | |
| 3 | Capacity | How many machines or people work in parallel. | 1 |
| 4 | Efficiency | Percentage of the time that is productive. | 100 |
| 5 | Shop Calendar Code REQUIRED | Working days and hours. Capacity on the board comes from it. | |
| 6 | Calculate Calendar REQUIRED | Action on the work center and machine center cards. Creates the calendar entries for a period. No calendar entries = zero capacity on the board and in Capacity Load. |
Important: Calendar entries run out. Recalculate the calendars regularly (for example monthly, from the job queue), otherwise capacity drops to zero at the end of the period and every operation after it looks overloaded.
Note: A machine that two companies use, such as one bonding line in a shared building, is set up as a machine center in each company. Shared Machines then joins them.
Set Up Manufacturing & the Planning Worksheet
Chain Planning runs Calculate Regenerative Plan and Carry Out Action Message in each company. These standard settings decide how that plan is calculated.
-
Choose the Search (Tell me) icon, enter Manufacturing Setup, and fill in the fields below.
-
Enter Planning Worksheet. In Name, create a batch such as DGB-APS — one per company, used only by Chain Planning.

Manufacturing Setup
| Field | Description | Default | |
|---|---|---|---|
| Planning (Manufacturing Setup) | |||
| 1 | Combined MPS/MRP Calculation | Plans finished items and components in one run. Chain Planning calculates the plan this way. | On |
| 2 | Components at Location | Location of components when the item has none. Match it with where stock is. | |
| 3 | Default Safety Lead Time | Buffer between the need date and the due date of supply. | 1D |
| 4 | Current Production Forecast | Leave blank unless you plan on forecast; the apps plan on orders. | |
| 5 | Default Dampener % | Tolerance before planning suggests a change. Keep 0 so every change shows up. | 0 |
| Numbering & Times | |||
| 6 | Firm Planned Order Nos. REQUIRED | Number series for firm planned production orders that Carry Out creates. | |
| 7 | Normal Starting / Ending Time | Default times of a production day. | |
| Planning Worksheet | |||
| 8 | Worksheet template and batch REQUIRED | A template of type Planning and a batch of its own in every company. Chain Planning recalculates this batch each run, so planners’ own batches stay untouched. |
Part B - Centralised Production Planning
This lets a planning company see stock and production capacity in every production company, and source planning lines from the right plant through intercompany.
Mark the Production Companies
Each plant says that it is a plant. Planning companies then find it automatically.
To mark a production company:
-
Sign in to the production company.
-
Choose the Search (Tell me) icon, enter Company Information, and then choose the related link.
-
On the General FastTab, in the Centralised Production Planning group, fill in the fields.
-
Repeat in every production company. In planning (sales) companies, leave Is Production Company off.

Company Information
| Field | Description | Default | |
|---|---|---|---|
| 1 | Company Code | A short code for the company. Planning companies show it next to the company name in availability views. | |
| 2 | Is Production Company REQUIRED | Marks the company as a plant that manufactures for the group. Discover Production Companies in planning companies finds the plants by this flag, and the availability FactBox is hidden in production companies. | Off |
Note: A company can be a production company and still plan, as level 2 does: it produces mats and sources carpet from level 3. Set Is Production Company on, and also set up CPP Setup there with level 3 as its production company.
Use the Guided Setup
The guide Set Up Centralised Production Planning does the next two pages for you in about five minutes. Run it in every planning company; in a production company it only sets the flag of the previous page.
-
Choose the Search (Tell me) icon, enter Assisted Setup, and choose Set Up Centralised Production Planning. You can also start it from Centralised Production Planning Setup with Set Up Production Planning (Guided).
-
Follow the steps in the table. Choose Next after each step and Finish at the end.

Set Up Centralised Production Planning
| Step | What you do | Sets | |
|---|---|---|---|
| 1 | Before you start | Check the prerequisites: IC partners, IC vendors, same item numbers. | — |
| 2 | What does this company do? | Production company or planning company, and the Company Code. | Company Information |
| 3 | Production companies | Find Production Companies adds every plant and maps its IC vendor from the IC partner code. Check the list and the priorities. | Production companies |
| 4 | Quantities | Available or total inventory, sub-assemblies, BOM levels. | Calculation fields |
| 5 | Items in step | Same Item No. or MDS Master Data Sync. | Item Link Provider |
| 6 | You’re all set | Finish, then set your role to Production Planner (Group). | — |
You can run the guide again at any time; it only adds what is missing.
Actions on Centralised Production Planning Setup
| Action | What it does |
|---|---|
| Discover Production Companies | Adds every company marked as a production company and maps its IC vendor. |
| Set Up Production Planning (Guided) | Opens this guided setup. |
| Production Readiness | Checks that items, BOMs, components and routings exist in every plant. |
| Production Company Availability | Exports stock, available quantity and Qty. Able to Make per plant to Excel. |
Centralised Production Planning Setup
One setup page per planning company. The top half decides how quantities are calculated; the bottom half lists the production companies (next page).
-
In a planning company (level 1, or level 2 when it sources from level 3), choose the Search (Tell me) icon, enter Centralised Production Planning Setup, and then choose the related link.
-
Fill in the fields. The defaults suit most companies.

Centralised Production Planning Setup
| Field | Description | Default | |
|---|---|---|---|
| Calculation | |||
| 1 | Use Available Inventory | Calculates with available inventory (inventory minus quantities reserved against it) instead of total inventory. Recommended: On, so stock promised to other orders is not offered twice. | On |
| 2 | Include Sub-Assembly Capacity | Qty. Able to Make also counts sub-assemblies the plant can still produce from stock, not only sub-assemblies already in stock. More realistic for multi-level BOMs. | On |
| 3 | Max. BOM Levels | How many production BOM levels are exploded. Also protects against circular BOMs. Raise it only for very deep structures. | 10 |
| 4 | Default Location Filter | Locations that count as stock in production companies that have no filter of their own, for example MAIN|FG. Blank = all locations. | Blank |
| Item Link | |||
| 5 | Item Link Provider | How items are matched across companies. Same Item No. (manual): you create items with the same number everywhere. MDS Master Data Sync (needs the MDS Connector): missing items, BOMs and routings can be requested from the master. | Same Item No. |
| Planning Worksheet | |||
| 6 | Show FactBox in Planning Worksheet | Shows the Production Company Availability FactBox next to the planning lines in this company. | On |
| 7 | Calculate Qty. Able to Make in FactBox | Calculates Qty. Able to Make whenever you move to another line. Turn off for very deep BOMs if the FactBox feels slow; the value is still calculated when you drill down. | On |
Add the Production Companies
The Production Companies part of the setup page lists the plants this company can see and source from.
To add production companies:
-
On Centralised Production Planning Setup, choose Discover Production Companies. Every company with Is Production Company is added, and its IC vendor is found from the IC partner code.
-
Check IC Vendor No. on each line; fill it in where it is blank.
-
Set Priority and, if needed, Location Filter.

Production Companies
| Field | Description | Default | |
|---|---|---|---|
| 1 | Company Name REQUIRED | The Business Central company that manufactures the items. | |
| 2 | Display Name | Name shown in the FactBox, on the report and in the company list. | Company name |
| 3 | Enabled | Includes the company in availability and sourcing. Turn off to stop sourcing from a plant without deleting it. | On |
| 4 | Priority | Sourcing priority. Auto-Source prefers lower numbers when several plants can cover the demand. | 0 |
| 5 | IC Vendor No. REQUIRED | The vendor in this company that represents the plant. Planning lines sourced from the plant get this vendor, so Carry Out creates an intercompany purchase order. | |
| 6 | IC Partner Code | The IC partner code of that vendor. Blank = purchase orders to the vendor are not sent through intercompany. | From vendor |
| 7 | Location Filter | Locations in the plant that count as stock, for example MAIN|FG. Blank = Default Location Filter, or all locations. | Blank |
Note: In a three-level chain, the sales company lists only level 2. Level 3 is listed in level 2’s own CPP Setup.
Item Link & Production Readiness
Sourcing works only when the plant knows the item: the item, its production BOM, every component and the routing must exist there. Production Readiness checks this before you send work to a plant.
Item Link Provider
| Value | When to use | What happens when something is missing |
|---|---|---|
| Same Item No. (manual) | Items are created by hand, or by another tool, with the same number in every company. | Readiness shows what is missing; you create it in the plant. |
| MDS Master Data Sync | MDS Master Data Sync and the MDS Connector are installed. | Readiness requests the missing item, BOM or routing from the MDS master with one action. |
To check readiness:
-
On the planning worksheet, select lines and choose Production Company › Check Production Readiness. Or open Production Readiness from the setup page or the role center.
-
Review the lines. A red status means the plant cannot produce the item yet.
-
Create the missing records, or request them from the master (MDS).

Production Readiness
| Column | Meaning | |
|---|---|---|
| 1 | Item No. | The item on the planning line. |
| 2 | Production Company | The plant checked. |
| 3 — 6 | Item, Production BOM, Components, Routing | Whether each exists in the plant, and whether the BOM and routing are certified. |
| 7 | Status | Ready, or what is missing. |
What CPP Adds to the Planning Worksheet
After setup, planners work on the standard Planning Worksheet. CPP adds one field, a FactBox and a group of actions.

Production Worksheet
| Element | What it does | |
|---|---|---|
| 1 | Source Production Company (field) | The plant the line is sourced from. Set by the two sourcing actions together with the plant’s IC vendor. |
| 2 | Production Company Availability (FactBox) | Per plant: inventory, available quantity and Qty. Able to Make for the item of the current line. Controlled by Show FactBox. |
| 3 | Qty. Able to Make | How many the plant can make from its component stock (and sub-assemblies, if set up). Drill down for the BOM explosion. |
| 4 | Source from Production Company | Choose a plant for the current line. The line becomes a purchase from the plant’s IC vendor. |
| 5 | Auto-Source Selected Lines | Picks the highest-priority plant that covers the quantity from stock, then from stock plus what it can make. |
| Split Line | Splits a line into several with the same total, for example over two plants or batches. | |
| Check Production Readiness, Production Company Availability, Production Planning Setup | See Production Readiness and CPP Setup. |
Note: With Advanced Planning, Chain Planning runs the sourcing step for you (Source from Group) in every company, in chain order.
Part C - Advanced Planning
The group planning board, Chain Planning across companies, shared machines and board views. Advanced Planning Setup is per company; the planning group, shared machines and board views are shared by all companies.
Advanced Planning Setup: Planning Board
The Planning Board FastTab sets how the board opens in this company. Users can change most of it on the board itself.
-
Choose the Search (Tell me) icon, enter Advanced Planning Setup, and then choose the related link. The page is created with defaults when the app is installed.
-
Fill in the Planning Board FastTab.
-
Repeat in every company where people open the board.

Advanced Planning Setup - Planning Board
| Field | Description | Default | |
|---|---|---|---|
| 1 | Days Back | How many days before the work date the board shows by default. Late orders older than this are still found with Go to orders. | 7 |
| 2 | Days Ahead | How many days after the work date the board shows. Match it roughly with your order book. | 60 |
| 3 | Include Planning Suggestions | Shows planning worksheet lines as dashed bars and uses them as supply in pegging. Turn off to see only real orders. | On |
| 4 | Show Operations | Shows the operations (routing lines) under each production order. Needed for the machine view and capacity load. | On |
| 5 | Auto Refresh (Seconds) | Refreshes the board on its own, for example 300 on a wall screen. 0 = only when you choose Refresh. | 0 |
| 6 | Max. Trace Levels | How many supply levels Supply Chain Trace follows across companies. | 10 |
| 7 | Warn When No Single Lot Covers | Warns on the board and in the trace when no single lot of a lot-tracked component covers the need, for example to keep one colour per job. | On |
| 8 | Default Board View | The board view the planning board opens with. Use it to show only one product line. | Blank |
Advanced Planning Setup: Chain Planning
Chain Planning plans every company of the group in chain order with one action. In each company it runs these steps, using the settings on this FastTab:
| Step | What happens |
|---|---|
| 1 Accept IC Inbox | Accepts incoming IC orders, so demand from the level above is there. |
| 2 Calculate Plan | Calculate Regenerative Plan on the batch, for the plan horizon. |
| 3 Source from Group | CPP sourcing: lines for items made in a plant become IC purchases from that plant. |
| 4 Carry Out | Accepts and carries out the action messages: orders are created and changed. |
| 5 Send IC Orders | Sends the new IC purchase orders to the next company. |

Advanced Planning Setup - Chain Planning
| Field | Description | Default | |
|---|---|---|---|
| 1 | Planning Worksheet Template REQUIRED | The planning worksheet template (type Planning) Chain Planning uses in this company. | |
| 2 | Planning Worksheet Batch REQUIRED | The batch Chain Planning calculates and carries out. Use a batch of its own. | |
| 3 | Plan Horizon (Days) | How many days ahead from the work date the plan is calculated. Longer = slower; shorter = late orders beyond the horizon are not planned. | 90 |
| 4 | Carry Out Automatically | Carries out the action messages (creates and changes orders) in this company. Turn off to review the worksheet before anything is created; Chain Planning then stops after Calculate Plan in this company. | On |
| 5 | Send IC Orders Automatically | Sends new intercompany purchase orders to the partner right away, so the next company in the chain has the demand for its own run. | On |
Important: Fill in template and batch in every company of the planning group. A company without them fails at step 2, and the companies below it get no demand.
Note: Chain Planning plans as of your work date, in every company of the group.
Advanced Planning Setup: Priorities & Scheduling
These rules decide how the board shares stock and machine time between orders, and how far it may move work on its own.
-
Choose the Search (Tell me) icon, enter Advanced Planning Setup, and open the Priorities and Scheduling FastTab.
-
Fill in the fields as described in the table.

Advanced Planning Setup - Priorities & Scheduling
| Field | Description | Default | |
|---|---|---|---|
| 1 | Allocate Stock by Priority | Free stock and existing supply go to Rush and High orders first, then Normal and Low, each by date. When off, they go to orders by date only: first come, first served. Reserved stock always stays with its order. | On |
| 2 | Frozen Zone (Days) | Orders and operations that start within this many days from today are frozen: Push Dependent Orders, Expedite and sequencing leave them where they are. You can still move them yourself. Use it for work that is already prepared on the shop floor. | 0 |
| 3 | Skip Days Without Capacity | Sequencing and promise dates skip days on which a machine has no capacity in its calendar: weekends, holidays, a breakdown. | On |
| 4 | Safety Days in Promise Date | Days added to a promise date as a buffer between the end of production and shipment. | 1 |
Planning Priority on Orders
The sales order and the production order get a field Planning Priority on the General FastTab: Rush, High, Normal (default) or Low. Sales or customer service set it on the sales order; planners can also set it on the board. A production order on Normal takes the most urgent priority of the customer orders it supplies.
Tip: Agree with sales who may set Rush. When every order is rush, none is: keep it for the few orders that must go first.
Set Up the Planning Group
The planning group lists every company that the board shows and Chain Planning covers. It is shared: one list for all companies.
-
Choose the Search (Tell me) icon, enter Planning Group, and then choose the related link.
-
Choose Add Production Companies. It adds the current company (level 1, Sales) and the production companies of CPP Setup (level 2, Production).
-
Correct the levels: in a three-level chain, set the carpet plant to 3.
-
Set Short Name and Board Colour for each company.

Planning Group
| Field | Description | Default | |
|---|---|---|---|
| 1 | Company Name REQUIRED | A company that takes part in group planning. | |
| 2 | Display Name | Name shown on the board and in the trace. | Company name |
| 3 | Short Name | Short label on bars, chips and row headers, for example SALES, MATS, CARPET. Keep it under 8 characters. | Company name |
| 4 | Role | Sales / Trading, Production, or Sales and Production. Shown on the board; helps planners read the chain. | Sales |
| 5 | Chain Level REQUIRED | Position in the supply chain. Level 1 receives customer orders, level 2 supplies level 1, and so on. Chain Planning runs the companies in this order. | 1 |
| 6 | Enabled | Shows the company on the board and includes it in Chain Planning. | On |
| 7 | Board Colour | Colour of this company on the board, for example #2F6FD0 for blue. Choose clearly different colours. | Automatic |
Tip: Two companies can share a level when they both supply the level above. Chain Planning runs them one after the other.
Set Up Shared Machines
When companies share a building and a machine, each company has its own machine center for it, and each sees only its own load. A shared machine joins them: the board shows the combined load on one row, and Capacity Conflicts finds clashes between companies.
-
Choose the Search (Tell me) icon, enter Shared Machines, and then choose the related link.
-
Create a line per shared machine.
-
In Company Machines, add one line per company that uses it, and mark one as Owner.

Shared Machines
| Field | Description | Default | |
|---|---|---|---|
| Shared machine | |||
| 1 | Code REQUIRED | Code of the shared machine or line. | |
| 2 | Description | Free text. | |
| 3 | Members | How many company machine centers or work centers represent it. Calculated. | |
| Company Machines (members) | |||
| 4 | Company Name REQUIRED | The company whose work center or machine center represents the shared machine. | |
| 5 | Capacity Type REQUIRED | Work Center or Machine Center. | Work Center |
| 6 | No. REQUIRED | The work center or machine center in that company. | |
| 7 | Owner (Capacity) REQUIRED | This member’s calendar is the real capacity of the machine. The load of all members is compared with it. Set exactly one owner. | Off |
Note: Optional. Without shared machines, the board shows each company’s machine centers on their own rows.
Set Up Board Views
A board view is a saved way of looking at the board: which companies, items and machines, which period and what to show. Views are shared by all companies. Planners choose a view in the View field on the board: Default Board View sets the one it opens with.
-
Choose the Search (Tell me) icon, enter Board Views, and then choose the related link.
-
Create a line per view. The fields are described here and on the next page.

Board Views
| Field | Description | Default | |
|---|---|---|---|
| 1 | Code REQUIRED | Code of the view. | |
| 2 | Description | What the view is for. | |
| 3 | View Type | Orders by company: one group per company. Machines and work centers: one row per machine with its load strip. Customer orders and their supply: each customer order with its whole supply chain under it. | Orders by company |
| 4 | Company Filter | Group companies the view shows, for example SALES CO|MAT PLANT. Blank = all. | Blank |
| 5 | Item Filter | Items the view shows. Use it to show only one product line or customer range. | Blank |
| 6 | Work/Machine Center Filter | Work centers, machine centers or shared machines the view shows. Mainly for the machine view. | Blank |
| 7 | Days Back | Days before the work date. | 7 |
Board Views: Display Fields & Recommended Views
Fields 8—14 of the Board Views list decide the period and what the board draws.
| Field | Description | Default | |
|---|---|---|---|
| 8 | Days Ahead | Days after the work date. | 60 |
| 9 | Zoom | Time scale the view opens with: Day, Week or Month. | Week |
| 10 | Show Dependencies | Draws arrows between supplying and consuming orders. | On |
| 11 | Only Late or At Risk | Shows only orders that are late, or at risk because something they depend on is late. Good for a daily exceptions view. | Off |
| 12 | Show Planning Suggestions | Shows planning worksheet lines as dashed bars. | On |
| 13 | Show Operations | Shows operations under production orders. | On |
| 14 | Auto Refresh (Seconds) | Refreshes the view on its own, for example 300 on a wall screen. 0 = manual. | 0 |
Recommended Views
| Code | View Type | Filters and options | For |
|---|---|---|---|
| GROUP | Orders by company | No filters | The planning office: everything, grouped by company. |
| ORDERS | Customer orders and their supply | Item filter on your product line | Sales and customer service: each customer order with its supply, red when late. |
| MACHINES | Machines and work centers | Resource filter on the line; Zoom Day; Auto Refresh 300 | Wall screen on the shop floor. |
| LATE | Orders by company | Only Late or At Risk; Days Back 30 | Daily exception list. |
Tip: To focus on one product line, create a view with an Item Filter and make it the Default Board View. All other orders in the companies stay out of sight.
Where the Apps Add Actions
These actions need no setup. Use this table to find them, and to check that every planner sees them.
| Page | Action | Opens |
|---|---|---|
| Role center Production Planner (Group) | ||
| Role Center | Planning Board (part and action), Run Chain Planning | The board; Chain Planning for the group. |
| Role Center > Advanced Planning | Chain Planning Runs, Shared Machines, Capacity Conflicts, Reschedule Requests, Board Views, Planning Group, Advanced Planning Setup | The pages of this part. |
| Standard pages | ||
| Sales Order | Supply Chain Trace, Show on Planning Board | Trace of the order across companies; the board focused on the order. |
| Sales Order Subform (lines) | Supply Chain Trace | Trace of the selected line. |
| Firm Planned and Released Prod. Order | Supply Chain Trace, Show on Planning Board | Where the order’s output goes and what it needs. |
| Item Card | Lot Availability | Lots in every company and single-lot advice. |
| Planning Worksheet | Advanced Planning › Planning Board, Run Chain Planning | Board and Chain Planning from the worksheet. |
| Planning Worksheet | Production Company group (CPP) | |
| Centralised Production Planning Setup | MDS Setup, MDS Sync Log, Link Planning Items Now | Only with the MDS Connector. |
Pages Without Setup Fields
These pages show results and need no setup: Chain Planning Runs and its steps, Reschedule Requests, Capacity Load, Capacity Conflicts, Supply Chain Trace, Lot Availability, What-If Changes. They are described in the user guide.
Verify the Setup
Three checks prove that the setup works from end to end. Run them in the level 1 company with one sales order for a produced item.
Production Readiness
Open Production Readiness and check that every item is Ready in every plant.
Run Chain Planning
-
Choose Run Chain Planning on the role center and confirm.
-
In Chain Planning Runs, wait until the run is Completed: five steps per company, all green.

Chain Planning Runs
| If a step fails | Check |
|---|---|
| Accept IC Inbox | IC partner Inbox Type and Inbox Details; the IC customer exists. |
| Calculate Plan | Template and batch in Advanced Planning Setup; item Reordering Policy. |
| Source from Group / Carry Out | IC Vendor No.; number series in Manufacturing Setup. |
| Send IC Orders | IC Partner Code on the vendor; Intercompany Setup of the partner. |
Planning Board
Open the Planning Board with the Customer orders and their supply view. The sales order shows its IC orders and production orders in the other companies underneath, linked by arrows.
Part D - Optional Apps & Checklist
The optional MDS Connecto, the Production Planning Board for a single company, and a checklist to sign off the setup company by company.
Set Up the MDS Connector (Optional)
With MDS Master Data Sync, one master company owns items, BOMs and routings and sends them to the other companies. The connector lets CPP ask the master to resend what a plant is missing.
-
Make sure MDS Master Data Sync is set up, with a master company and the receiving companies, and that the MDS Connector is installed.
-
On Centralised Production Planning Setup, set Item Link Provider to MDS Master Data Sync.
-
Check the MDS Master field: it shows how this company reaches the master.
-
Optional: ask your administrator to run Link Planning Items Now every night from the job queue.

Centralised Production Planning Setup
| Field | Description | Default | |
|---|---|---|---|
| 1 | Item Link Provider REQUIRED | MDS Master Data Sync — value added by the connector. | Same Item No. |
| 2 | MDS Master | Read-only. How this company reaches the MDS master that is asked to resend missing items, BOMs and routings. | |
| 3 | MDS Setup (action) | Opens MDS Master Data Sync setup for this company. | |
| 4 | MDS Sync Log (action) | MDS service calls and sync events, including resend requests from CPP. | |
| 5 | Link Planning Items Now (action) | Checks every item on the planning worksheets against the plants and requests anything missing. It can also run every night on its own. |
Caution: Exclude the per-company planning fields from the MDS item sync (Replenishment System, Vendor No., Manufacturing Policy, Routing No., Production BOM No., Reordering Policy). Otherwise MDS overwrites the role of the item in each company.
Production Planning Board for One Company
Companies that plan production in one company can use d365 Production Planning Board on its own. It is the same board with the same functions as Part E, without anything that spans companies.
| Function | Advanced Planning (group) | Production Planning Board (one company) |
|---|---|---|
| Board views: customer orders, orders, machines | Yes, all companies | Yes |
| Move orders and operations, impact on linked orders | Yes, across companies | Yes |
| Priorities, Expedite, Sequence machines | Yes | Yes |
| Move operations to another machine | Yes | Yes |
| Shortages, Order Coverage, Promise dates | Yes | Yes |
| Frozen zone, started work | Yes | Yes |
| Chain Planning, intercompany links | Yes | No |
| Planning group, shared machines | Yes | No |
| Needs Centralised Production Planning | Yes | No — no other app needed |
To set it up:
-
Your administrator installs d365 Production Planning Board and gives planners the permission set DGB PPB.
-
Choose the Search (Tell me) icon, enter Production Planning Board Setup: the same fields as the planning board FastTab and priorities and scheduling.
-
Create board views if you like, and open Production Planning Board from Tell me or the Production Planner home page.
Note: Prerequisites are the same as Part A for one company: items with routings and production BOMs, machine centers with calendars, and a planning worksheet.
Setup Checklist Per Company
Print this page and tick each line per company. ✔ = needed in that company. You can click on the link under the Page column to get to the setup information.
| Setup | Level 1 Sales | Level 2 Plant | Level 3 Plant | Page |
|---|---|---|---|---|
| Business Central | ||||
| Intercompany Setup: IC Partner Code, Inbox Type Database | ☐ | ☐ | ☐ | Intercompany |
| IC partner for each neighbour in the chain | ☐ | ☐ | ☐ | IC partners |
| IC vendor for the level below | ☐ | ☐ | — | IC vendors |
| IC customer for the level above | — | ☐ | ☐ | IC customers |
| Items with the same numbers; replenishment per role | ☐ | ☐ | ☐ | Items |
| Certified BOMs and routings | — | ☐ | ☐ | Items |
| Work centers, machine centers, calendars calculated | — | ☐ | ☐ | Capacity |
| Manufacturing Setup; planning batch DGB-APS | ☐ | ☐ | ☐ | Manufacturing |
| Centralised Production Planning | ||||
| Company Information: Is Production Company, Company Code | — | ☐ | ☐ | Company Info |
| CPP Setup: calculation and item link | ☐ | ☐ | — | CPP Setup |
| Production companies with IC Vendor No. | ☐ | ☐ | — | Prod. companies |
| Advanced Planning | ||||
| Advanced Planning Setup: board defaults | ☐ | ☐ | ☐ | APS Setup |
| Advanced Planning Setup: template, batch, horizon | ☐ | ☐ | ☐ | Chain Planning |
| Planning Group (once): levels 1—3 | ☐ | Planning Group | ||
| Shared machines (once, optional) | ☐ | Shared Machines | ||
| Board views and default view (once) | ☐ | Board Views | ||
| Users | ||||
| Permission sets in every company | ☐ | ☐ | ☐ | Permissions |
| Role Production Planner (Group) | ☐ | ☐ | ☐ | Role center |
| Verified: readiness, chain run, board | ☐ | Verify |
Part E - Using the Planning Board
The Planning Board shows the orders of every company in the group on one timeline: customer orders, the intercompany orders between the companies, production orders with their operations, and purchases. You see which orders are late, why, and what happens when you change a date.
Open the Board & Choose What To See
-
On the home page, choose Planning Board. You can also open it from a sales order, a production order or the planning worksheet with Show on Planning Board; the board then opens on that order.
-
In View, choose a saved view, and in Show, choose how to group the orders.
-
Set Move Supply with Order and Push Dependent Orders before you move anything.

Planning Board
| Field | Description | Default | |
|---|---|---|---|
| 1 | View | The saved board view: which companies, items and dates. Blank = the default view. | Default view |
| 2 | Show | Orders by company, Machines and work centers, or Customer orders and their supply. | From the view |
| 3 | Move Supply with Order | When you move an order, every order that supplies it moves by the same number of days, in every company. | On |
| 4 | Push Dependent Orders | When you move an order later, the orders that need it are pushed out by the delay, up to the customer order. | On |
| 5 | Selected | The order or operation you clicked. | |
| 6 | What-If Changes | How many orders you moved. Nothing is saved until you choose Apply Changes. | |
| 7 | Loaded | When the board was loaded, and how many orders it holds. |
| Menu | Actions |
|---|---|
| Board | Refresh, Apply Changes, Discard Changes, Show Changes, Order Coverage |
| Selected Order | Change Date…, Supply Chain Trace, Open Document, Lot Availability, Set Priority…, Expedite Order…, Promise Date… |
| Capacity | Move to Machine…, Sequence All Machines, Level Load Machine, Capacity Conflicts, Capacity Load |
| Plan | Run Chain Planning, Chain Planning Runs, Reschedule Log, and the setup pages |
Find Orders: Toolbar and Filters
The toolbar at the top of the board moves the timeline and filters the orders. Under it, one chip per company hides or shows that company.

Planning Board - Toolbar
| Button | What it does | |
|---|---|---|
| 1 | Day, Week, Month | Time scale of the timeline. |
| 2 | Today | Scrolls to the work date. A vertical blue line marks it. |
| 3 | Go to orders | Scrolls to where the orders are, for example when they are far from today. |
| 4 | Next late ▶ | Selects the next late order and scrolls to it. |
| 5 | Expand all / Collapse all | Opens or closes what is under every order. Use ▸ / ▾ in front of one order for that order only. |
| 6 | Links | Shows or hides the arrows between supplying and consuming orders. |
| 7 | Late only | Only late (red) and at-risk (amber) orders. |
| 8 | Search | Type an order number or item; matching orders stay, with what is under them. |
| 9 | ? Help | A short help panel on the board itself. |
| 10 | Refresh | Reloads the board from all companies. Moves you have not applied are lost. |
| 11 | Full screen | Uses the whole screen, for example on a wall monitor. |
| 12, 13 | Company chips, Clear filters | Hide a company; switch every filter off in one click. |
Read the Board
With Show = Customer orders and their supply, each customer order has its whole supply chain under it, across the companies. This is the example used on the next pages.

Planning Board - One Customer Order
| You see | Meaning | |
|---|---|---|
| 1 | Order row | Its coloured left edge shows the company (colour from the planning group). |
| 2 | Indent and ▸ / ▾ | What is under an order supplies it: the IC order, the production order, its operations and components. |
| 3 | Bar of a customer order | Shipment date. Sales, intercompany, production and purchase orders each have their own colour. |
| 4 | Bar of a production order | From starting to ending date; its operations are underneath. |
| 5 | Dashed grey bar | A planning worksheet suggestion, not an order yet. |
| Red outline | Late because of its own dates: it is ready after it is needed. | |
| Amber outline | At risk: its own dates are fine, but something it waits for is late. | |
| Thin red line with +N d | How many days late the order will be ready. | |
| Dashed blue outline | You moved it; not saved yet. |
| Show | Use it to |
|---|---|
| Customer orders and their supply | Follow one customer order through every company. Orders not linked to a customer order are in a group at the end. |
| Orders by company | See all orders of each company together. |
| Machines and work centers | See operations per machine, with the daily load. |
Select an Order
Click an order’s name, its bar or its red line. A blue strip above the board shows the order and what you can do with it.

Planning Board - Selected Order
| Button | What it does | |
|---|---|---|
| 1 | Change date… | Asks for the new date, and whether supply and dependent orders move too. |
| 2, 3 | ◀ 1 day, 1 day ▶ | Moves the order one day earlier or later. |
| 4 | Trace | Follows the supply of the order through every company. |
| 5 | Open | Opens the document. Orders of another company open in a new browser tab, in that company. |
| 6 | Lots | Free lots of the item or its lot-tracked components, in every company. |
| 7 | × | Clears the selection (Esc). |
| 8 — 10 | Priority…, Expedite…, Promise date… | For an operation, Machine… appears instead. |
Other Ways to Move an Order
| Do this | To |
|---|---|
| Drag the bar | Move the order to another date. |
| Drag the right edge of a bar | Make a production order or operation longer or shorter. |
| Left / right arrow key | Move one day earlier / later. |
| Shift + left / right arrow | Move one week. |
| Enter / Esc | Open the Change Date dialog / clear the selection. |
Note: Every move is a what-if. The board shows the effect at once, but nothing is saved in Business Central until you choose Apply Changes.
Change the Date of a Production Order
Example: the bonding line at MAT PLANT needs three more days for production order FP-4004.
-
Open the board with Show = Customer orders and their supply, and expand SO-1004.
-
Click FP-4004 and choose Change date… in the blue strip.
-
Enter the New Date, three days later. Choose whether the supply moves and whether the orders that need it are pushed.
-
Choose OK. The board shows the result at once; see the next page.
-
Choose Apply Changes to save it, or Discard Changes to undo.

Change Date
| Field | Description | Default | |
|---|---|---|---|
| 1 | Order | The order you selected. | |
| 2 | Current Date | The current date: end date of a production order or operation, shipment date of a sales order, receipt date of a purchase. | |
| 3 | New Date | The date to move to. | |
| 4 | Days Moved | How many days it moves. Negative = earlier. | |
| 5 | Move Its Supply Too | Everything that supplies this order moves by the same number of days: component purchases, IC orders and production orders in other companies. Stock does not move. | Board setting |
| 6 | Push Dependent Orders | When the order moves later, the orders that need it are pushed out by exactly the delay, up to the customer order. | Board setting |
Tip: The two switches start with the values of Move Supply with Order and Push Dependent Orders above the board, so set those once for your way of working.
How a Change Reaches the Linked Orders
The same move of FP-4004, three days later, with Push Dependent Orders off and on. The board works out the effect on every linked order in every company.
Push Dependent Orders off: the board shows who is affected

Planning Board — Production order moved, not pushed
| Order | Company | What you see | |
|---|---|---|---|
| 1 | FP-4004 production order and its operations | MAT PLANT | Dashed blue: moved three days. |
| 2 | SO-3004 IC sales order | MAT PLANT | Amber: its production order is now late. |
| 3 | PO-2004 IC purchase order | SALES CO | Amber: its supplier in MAT PLANT is late. |
| 4 | SO-1004 customer order | SALES CO | Red, +3 d: the hotel gets it three days late. |
Push Dependent Orders on: the linked orders move with it

Planning Board — Production order moved and pushed
SO-3004 1 and its other half PO-2004 2 move three days, and so does the shipment date of SO-1004 3 . After Apply Changes, the new dates are in all three documents. Tell the customer about the new date.
Change Sales & Purchase Dates
Any order can move: customer orders, intercompany orders, production orders, operations and purchases. Three rules decide what moves with it.
| Rule | When | What moves |
|---|---|---|
| 1. The other half of an intercompany order | Always | An IC purchase order and its IC sales order in the other company are one delivery: move one and the other follows. |
| 2. Move Supply with Order | Switch on | Everything under the order — IC orders, production orders, operations, purchases — moves by the same number of days, in every company. |
| 3. Push Dependent Orders | Switch on, and the order moves later | Everything above the order that needs it is pushed out by exactly the delay, up to the customer order. |
Examples
| You move | Switches | Result |
|---|---|---|
| Customer order SO-1004 5 days earlier (the hotel wants it sooner) | Supply off | Only SO-1004 moves. It turns red: its supply now arrives too late. Shows that the request cannot be met as is. |
| Customer order SO-1004 5 days earlier | Supply on | The whole chain moves five days earlier in all three companies. Red where an order would have to start before today. |
| Carpet purchase PO-5004 4 days later (supplier delay) | Push off | PO-5004 and its other half SO-6004 move. FP-4004 turns amber, then SO-3004 and PO-2004, and SO-1004 turns red. |
| Carpet purchase PO-5004 4 days later | Push on | FP-4004 and everything above it are pushed out by four days, up to the new shipment date of SO-1004. |
| Operation 10 on MC-BOND 1 day later | Push on | The operation moves; the production order ends a day later, and the orders above it are pushed by one day. |

Planning Board — Customer order earlier with its supply
1 SO-1004 moved, 2 its supply moved with it, 3 the carpet production order would have to start before today: red. That tells you how much earlier is possible.
Apply or Discard Your Changes
Moves on the board are what-if until you apply them. What-If Changes above the board shows how many orders you moved, and the board shows a WHAT-IF badge.
Check, Apply or Undo
-
Choose Board › Show Changes to see every moved order with its old and new dates.
-
To undo everything, choose Discard Changes. Refresh also discards.
-
To save, choose Apply Changes, and then Yes. Each change is written in the company that owns the order.
-
Answer Yes to run Chain Planning, so every company’s planning follows the new dates.

What-If Changes
What Apply Changes Writes:
| Order | Field that changes |
|---|---|
| Customer and IC sales order | Shipment Date on the line |
| IC and normal purchase order | Expected Receipt Date on the line |
| Production order | Starting Date-Time; Business Central reschedules the operations |
| Operation | Starting and ending date-time of the routing line |
| Planning worksheet line | Due Date |
Note: Released orders are reopened, changed and released again for you. Choose Plan > Reschedule Log to see every change and whether it was saved; a failed line shows why, for example a document waiting for approval.
Trace the Supply & Check Lots
Supply Chain Trace answers “why is this order late?”. It follows an order down through every order that supplies it, across the companies. Open it from the board (Trace), or from a sales or production order.

Supply Chain Trace
| Column | Meaning | |
|---|---|---|
| 1 | Level | 0 is the order you traced; 1 supplies it, 2 supplies 1, and so on. |
| 2 | Company | Where the order is. |
| 3, 4 | Needed By, Ready | When the order above needs it, and when it is ready. |
| 5 | Late | Ready after it is needed. The lowest late line is the cause. |
| 6 | Lots | For lot-tracked items: a warning when no single lot covers the need, and the suggested lot. |
Lot Availability
From the board (Lots) or the item card: the free lots of an item, or of its lot-tracked components, in every company, with an Advice line, for example to use one lot per job so the colour stays the same.
Check Capacity
Business Central plans production as if machines have unlimited hours, so two orders can sit on the same machine at the same time. The board shows where capacity runs out, so you can decide which orders will be late.
| Where | What it tells you |
|---|---|
| Show = Machines and work centers | One row per machine with its operations, and a load strip under it: green under 80 %, amber from 80 to 100 %, red above. A shared machine shows the operations of every company on one row. |
| Capacity > Capacity Load | Per machine and day: capacity hours from the calendar, load hours from all companies, load %, and whether it is overloaded. Includes your what-if moves. |
| Capacity > Capacity Conflicts | Every pair of operations on the same machine at the same time, with the overlap in hours. Cross-Company = clash between two companies on a shared machine. |
| Capacity > Level Load Machine | Select an operation first. Lines up all operations on its machine one after the other, so nothing overlaps. Operations pushed past their date turn their orders red, up to the customer order. |

Capacity Load
When a machine is overloaded:
-
Level Load Machine shows the realistic dates. Keep it if the late orders are acceptable, and choose Apply Changes.
-
Move an order to another day with Change date…, or move the customer order later and tell the customer.
-
Add capacity: an extra shift in the machine’s calendar. The board shows the new capacity after Refresh.
-
Discard Changes if you only wanted to see the effect.
Plan the Whole Chain
Run Chain Planning plans every company in chain order with one action: new customer orders become intercompany orders and production orders in all companies. Run it after new orders, and after Apply Changes.
-
Choose Run Chain Planning on the home page, the board (Plan) or the planning worksheet, and confirm.
-
Open Chain Planning Runs to follow it. Each company runs five steps, level 1 first.
-
When the run is Completed, choose Refresh on the board.
| Step | What happens in the company |
|---|---|
| Accept IC Inbox | Orders from the level above are accepted. |
| Calculate Plan | The planning worksheet is calculated. |
| Source from Group | Lines for items made in a plant become purchases from that plant. |
| Carry Out | Orders are created and changed. |
| Send IC Orders | New intercompany purchase orders go to the next company. |
| Status | Meaning and what to do |
|---|---|
| Running | Busy. Choose Refresh on Chain Planning Runs. |
| Completed | All steps done in all companies. |
| Failed | Open the run: the failed step shows the message. Fix the cause (see Verify the setup) and run again. |
Tip: Chain Planning plans as of your work date. Check the work date in My Settings before you run it.
Priorities & Rush Orders
Not every order is equal. A key customer’s urgent order should get stock, supply and machine time before a stock replenishment that can wait. The planning priority tells the board which orders go first.
| Priority | Badge | Meaning |
|---|---|---|
| Rush | RUSH | Goes before everything else: first pick of stock and supply, first on the machines. |
| High | HIGH | Before Normal and Low orders. |
| Normal | — | The default. Orders are served by date. |
| Low | LOW | Served last, for example stock replenishment or orders the customer can wait for. |
How priority flows through the plan:
-
A customer order has its own priority (field Planning Priority on the sales order).
-
The production orders, purchases and intercompany orders that supply it take the same priority, down the chain. A production order that serves a rush and a normal order is rush.
-
Operations take the priority of their production order, so a rush job goes first on every machine when you sequence.
-
In the Customer orders view, rush orders are listed at the top of each company.
To change a priority on the board:
-
Select a customer order or a production order, and choose Priority… in the blue strip (or Set Priority…).
-
Choose Rush, High, Normal or Low.
-
The board allocates stock and supply again, most urgent first, and shows the effect: an order that gets the stock turns green or on time, an order that loses it can turn SHORT or late.
-
Choose Apply Changes to write the priority on the order, or Discard Changes.
Note: Reserved stock is never taken from its order. If a rush order needs stock that is reserved for another order, the trace shows it; remove the reservation on that order first.
Expedite an Order: Who gains, who waits
Expedite Order… does what a planner does for a rush order, in one step, as a what-if: priority, stock, supply, machines. Then it lists every customer order whose date changed, so you see the price of the rush before you commit.
-
Select the customer order (or its production order) and choose Expedite….
-
Choose the steps in the dialog and choose OK.
-
Read the summary and the list Effect on Customer Orders: the expedited order at the top, then the orders that are earlier (green) or later (red).
-
Keep it with Apply Changes, or undo it with Discard Changes.

Expedite Order
| Field | Description | Default | |
|---|---|---|---|
| 1 | New Priority | The priority the order gets. Rush goes before everything else. | Rush |
| 2 | Give It Stock First | Free stock and existing supply go to this order before orders with a lower priority, even if they are due earlier. | On |
| 3 | Pull Its Supply Earlier | Its production orders and purchases move earlier by the days it is late, but not before today and not in the frozen zone. | On |
| 4 | Put It First on the Machines | Its operations go first on every machine they use; the other operations follow by priority and date. | On |
| 5 | Move the Delayed Orders Out | Customer orders delayed by this get new shipment dates. When off, they keep their dates and show red, so you decide per order. | Off |

Effect on Customer Orders
Move Work Between Machines
When a machine is overloaded or down, move operations to another machine of the same work center, or let the board plan each machine one job at a time.
Move one operation
-
Set Show to Machines and work centers. Every machine of a work center has a row, also the idle ones.
-
Drag the operation up or down onto another machine row. The bar turns green over a machine it may move to, red over one it may not.
-
Or select the operation and choose Machine…: a list shows each machine of the work center with the duration there, its capacity that day and the hours already planned.
-
The duration follows the new machine’s efficiency and capacity: a machine at 125 % does the same work in 80 % of the time.
-
Apply Changes writes the new machine on the routing line of the production order; Business Central recalculates the times.

Move to Machine
Plan Machines One Job at a Time
| Action | What it does |
|---|---|
| Level Load Machine | For the machine of the selected operation: one job at a time, most urgent first. |
| Sequence All Machines | The same for every machine on the board. Operations of an order stay in sequence; days without capacity are skipped; started and frozen work stays. |
Note: Operations planned on a work center (not on a machine) cannot move to a machine from the board. Started operations stay on their machine.
Shortages & Order Coverage
A finished product that is not in stock has to come from somewhere. The board tells you, per customer order, where it comes from and whether it is enough.
| Coverage | Badge on the board | What it means | What to do |
|---|---|---|---|
| From stock | label ends in « · from stock » | Stock that no other order has taken covers the whole order. | Nothing. Ship it. |
| Supply on time | — | A production order or purchase covers it and is ready in time. | Nothing. |
| Supply late | red outline, +N d | It is covered, but the supply is ready after the shipment date. | Expedite, move the supply, or agree a new date. |
| Partly short | PART SHORT | Part of the quantity has no supply at all. | Plan the rest, or ship part. |
| Short | SHORT | Nothing covers the order. | Run planning (or Chain Planning), or make a production order; give the customer a promise date. |
| Production order misses material | COMPONENTS | A component has no supply, or arrives after the production order needs it. | Trace it; expedite the purchase or the component’s production. |
Find Them
-
Shortages in the toolbar shows only short customer orders and production orders that miss components.
-
Order Coverage (Board menu) lists every customer order, most urgent first, with coverage, quantity from stock, short quantity and the date it can really ship.

Order Coverage
Promise Dates
When a customer asks “when can I have it?”, the promise date gives an answer you can keep. It never uses stock, supply or machine time that is already given to another order.
How the Date is Worked Out:
-
Free stock: Stock that no order has taken, now.
-
Free existing supply: Production orders and purchases already planned, with quantity no order has taken, on their date.
-
Make or buy the rest: Each component from free stock or supply, or made or bought itself (up to three BOM levels); bought items take their lead time.
-
Machine hours: Each operation of the routing is fitted into the free hours of its machine, day by day, after everything already on the board.
-
The last step done, plus the Safety Days in Promise Date, is the earliest shipment date. The step that decides it is marked Bottleneck.
Where to Use It:
| From | Then |
|---|---|
| The board: select a customer order, Promise date… | Use as Shipment Date moves the order on the board (what-if); Apply Changes writes it. |
| A sales order line: Promise Date (Stock and Capacity) | Use as Shipment Date writes the date on the line at once. |
| Tell me: Promise Date | Enter any item and quantity, for a quote or a phone call. |

Promise Date
Business Scenarios: What the Board Does
The situations a planner meets every week, and what the board does in each. All are what-ifs until Apply Changes.
| Situation | What you do | What the board does |
|---|---|---|
| Customer orders | ||
| Customer wants it earlier | Move the sales order earlier, Move Supply with Order on | Its supply moves too. Red where it would have to start before today: that is how much earlier is possible. |
| Customer accepts it later | Move the sales order later | Supply can stay (stock ready early) or move with it (frees capacity this week). |
| Rush order from a key customer | Expedite… | Stock first, supply earlier, first on the machines; list of orders that gain and wait. |
| New order, customer asks for a date | Promise date… | Earliest date from free stock, supply, components and free machine hours. |
| Finished product not in stock | Look at coverage | SHORT until planning creates supply; then Supply on time or late. |
| Production | ||
| Production order needs more time | Move it later, Push Dependent Orders on or off | On: everything above moves, up to the customer order. Off: they turn amber and the customer order red. |
| Machine overloaded | Sequence All Machines or Level Load Machine | One job at a time, most urgent first; the orders that become late turn red. |
| Machine down or busy | Drag operations to another machine of the work center | Duration follows the new machine; Apply writes the machine on the routing line. |
| Work already started | — | Started operations and orders do not move; the rest is planned around them. |
| Work for the next days is prepared | Set a Frozen Zone | Push, expedite and sequencing leave frozen work alone; you can still move it yourself. |
| Material | ||
| Supplier is late | Move the purchase later | Production orders that need it turn amber (COMPONENTS), customer orders red; Push moves them out. |
| Component missing | Look at COMPONENTS / Trace | Shows which component, how much is short and when it arrives. |
| Two orders want the same stock | Set priorities | Rush and High get it first; the other order turns SHORT or late. Reserved stock stays with its order. |