Centralised Production & Advanced Planning for Dynamics 365 Business Central User Guide

Are you ready to try the solution or have questions? Book a Teams Meeting

Introduction

This guide explains how to set up Centralised Production Planning (CPP) and Advanced Planning in Microsoft Dynamics 365 Business Central, and how to plan with the group planning board. This will cover every setup page and every field: what it does, its default, and what to enter. We also provide a section that shows planners how to use the board: change a date, see the effect on every linked order, apply the change and check capacity.

To get the app, visit the Microsoft Marketplace — d365 Centralised Production Planning for Business Central 

NOTE: This document is the V2 (version 2) of the original Centralised Production Planning app user guide. New features and updates are included that improves upon the application.

What The Apps Do

AppWhat it addsUsed in
Centralised Production PlanningStock and capacity of every production company on the planning worksheet; sourcing of planning lines from a production company through intercompany.Every company of the group
Advanced PlanningGroup planning board (Gantt) with pegging and impact, Chain Planning across companies, supply chain trace, shared machines, capacity load and lot advice.Every company of the group
MDS ConnectorOptional. Requests missing items, BOMs and routings from the master company.Companies that use MDS Master Data Sync
Production Planning BoardThe same planning board for a single company, without anything that spans companies.One company

Conventions

You seeMeaning
Bold textA page, field or action as it appears in Business Central.
Choose the Search (Tell me) iconUse Tell me (Alt+Q) to search for the page.
3A numbered callout. The same number marks the field on the screenshot and in the field table below it.
REQUIREDThe apps do not work without a value in this field.

Before You Start

Your administrator installs the apps and grants you access. You need a user who can open every company of the group. Set the companies up in the order on the next page.

How The Setup Fits Together

The apps plan supply along a chain of companies, connected by intercompany orders. Setup has three layers: standard Business Central in every company, CPP in the companies that plan, and Advanced Planning for the group.

Company Roles

LevelRole (example)What it does
1Sales company (SALES CO)Takes customer orders; buys from the plant through IC purchase orders.
2Production company (MAT PLANT)Receives IC sales orders, produces, buys components — also from level 3.
3Production company (CARPET PLANT)Supplies level 2, usually make-to-stock in lots.

Setup Order

Work in this order; each step depends on the one before. Once (shared) pages hold one set of data for all companies.

#StepCompaniesWhy
1Get access and set your roleAllYou can open every page of this guide.
2Intercompany Setup and IC PartnersAllIntercompany orders carry demand from one company to the next.
3IC vendors and customersAllPurchase orders go to a vendor; sales orders come from a customer.
4Items in every companyAllSame item numbers; replenishment system per role.
5Work centers, machine centers, calendarsProductionProduction orders and capacity load need calendars.
6Manufacturing Setup and planning worksheetAllPlanning parameters and the worksheet batch Chain Planning uses.
7Company InformationProductionMarks the plants so planning companies find them.
8CPP Setup and production companiesPlanningWhich plants a company sources from, through which IC vendor.
9Advanced Planning SetupAllBoard defaults and Chain Planning in each company.
10Planning Group, Shared Machines, Board ViewsOnce (shared)Which companies plan together and how the board looks.
11Verify the setupPlanningReadiness check, a chain run and the board.

Access & Role Center

Your administrator installs the apps once for the whole group. Before you start, check that you have the right access and the planner’s home page.

Access You Need

Permission setWho needs it
Centralised Prod. Planning - UserPlanners. Planners also need read access in every production company, to see items, BOMs and stock there.
Centralised Prod. Planning - AdminWhoever maintains the planning setup and the list of production companies.
d365 Advanced PlanningPlanners and key users who use the planning board, Chain Planning and the shared setup.
Centralised Prod. Planning - MDS ConnectorUsers who request missing items, BOMs or routings from the master company.

Important: Chain Planning and Apply Changes on the planning board update orders in the other companies for you. You therefore need planning, sales, purchase and production access in every company of the group.

Set Your Role

  1. Choose the Search (Tell me) icon, enter My Settings, and then choose the related link.

  2. In Role, choose Production Planner (Group), and then choose OK.

Your home page now shows planning, the planning board, Chain Planning and every setup page of this guide.



The home page: 1 planning board, 2 Chain Planning, 3 and 4 the setup pages.

Part A - Business Central Prerequisites

This is the Standard Business Central setup that the apps rely on. If intercompany, items and capacity already work in your companies, check the fields marked as important for the apps and move on.

Set Up Intercompany in Every Company

Demand travels down the chain as intercompany orders: a purchase order in the buying company arrives as a sales order in the selling company. That only works when every company has its own intercompany identity.

To set up intercompany:

  1. In each company, choose the Search (Tell me) icon, enter Intercompany Setup, and then choose the related link.

  2. Fill in the fields as described in the table.

  3. Repeat in every company of the group.



Intercompany Setup
FieldDescriptionDefault
1IC Partner Code REQUIREDThe code that identifies this company to its partners. Every other company uses this code in its IC partner list. Use a short, stable code per company.
2IC Inbox Type REQUIREDHow transactions reach this company. Choose Database: all companies are in the same environment, so intercompany documents are delivered directly to the inbox.File Location
3IC Inbox Details REQUIREDWith Database, the name of this company.
4Auto. Send TransactionsSends intercompany documents as soon as they are released or posted, without a stop in the outbox. Recommended: On. Chain Planning also sends new IC purchase orders itself when Send IC Orders Automatically.Off

Note: The page can show more fields, such as a default IC journal template and batch. You don’t need them for planning.

Set Up IC Partners

In every company, create an IC partner for each neighbour in the chain: level 1 needs level 2; level 2 needs levels 1 and 3; level 3 needs level 2.

  1. Choose the Search (Tell me) icon, enter Intercompany Partners, and then choose New.

  2. Fill in the fields, then repeat for the next partner.



Intercompany Partner Card

FieldDescriptionDefault
General
1Code REQUIREDThe partner company’s IC Partner Code from its own Intercompany Setup. Must match exactly.
2NameFree text.
3Data Exchange TypeChoose Database when both companies are in the same environment.Database
4Inbox Type REQUIREDMust be Database so documents go straight into the partner’s inbox.
5Inbox Details REQUIREDThe partner’s company name.
6Auto. Accept TransactionsAccepts incoming documents from this partner automatically. Chain Planning also accepts the IC inbox as its first step, so either works. Recommended: On.Off
Sales & Purchase Transactions
7Customer No.The customer in this company that represents the partner when it buys from you. Needed on partners that buy from this company.
8Receivables AccountG/L account for intercompany receivables. Needed to post.
9Vendor No.The vendor in this company that represents the partner when you buy from it. Needed on partners that supply this company.
10Payables AccountG/L account for intercompany payables.
11Outbound Purch. Item No. TypeWhich item number is sent on purchase documents. Internal No. works because item numbers are the same in every company. Use Common Item No. or Item Reference only if they differ.Internal No.

Set Up IC Vendors, Customers & Item Numbers

Every link in the chain needs a vendor on the buying side and a customer on the selling side, both with the partner’s IC Partner Code.

CompanyVendor (buys from)Customer (sells to)
Level 1 — sales companyV-IC-MATS → IC partner of level 2— (external customers)
Level 2 — mat plantV-IC-CARPET → IC partner of level 3C-IC-SALES → IC partner of level 1
Level 3 — carpet plant— (external suppliers)C-IC-MATS → IC partner of level 2

To set up the vendor and the customer:

  1. Open the Vendor Card (or create a vendor). On the General FastTab, set IC Partner Code.

  2. Fill in the usual posting groups, payment terms and so on, as for any vendor.

  3. Open the Customer Card in the selling company and set IC Partner Code the same way.



Vendor Card: 1 IC Partner Code. The customer card has the same field.

FieldDescription
1IC Partner Code (vendor) REQUIREDOn the vendor that represents a production company. Purchase orders to this vendor are sent through intercompany. CPP uses this vendor as the IC Vendor No. of the production company.
2IC Partner Code (customer) REQUIREDOn the customer that represents a buying company. Incoming IC sales orders are created for this customer.

Item Numbers

The apps find an item in another company by its number. Use the same item number, base unit of measure and item tracking code in every company that handles the item. With the MDS Connector, MDS keeps them in step.

Caution: If MDS or another tool copies items between companies, exclude the planning fields of the next page (Replenishment System, Vendor No., Manufacturing Policy, Routing No., Production BOM No.). They differ per company on purpose.

Set Up Items in Every Company

The same item plays a different role in each company: bought in the sales company, produced in the plant. The item card fields below decide what planning suggests in each company.



Item Card
FieldSales company (level 1)Production companyWhy
1Replenishment SystemPurchaseProd. OrderPurchase makes planning suggest a purchase; CPP turns it into an IC purchase from the plant.
2Vendor No.IC vendor of the plantBlank (or the IC vendor of the next level for bought components)Default vendor of the planning line. CPP can change it per line.
3Lead Time CalculationPlant lead time, e.g. 2DBlankPlanning dates the purchase this many days before the need.
4Manufacturing Policy—Make-to-Order for mats; Make-to-Stock for carpetMake-to-Order links the production order to the IC sales order: the board pegs and traces it.
5, 6Routing No., Production BOM No.BlankCertified routing and BOMProduction orders, operations on the board and capacity load.
7Reordering PolicyOrder or Lot-for-LotOrder (MTO) or Lot-for-LotWithout a policy the item is not planned.
8Include InventoryOnOnPlanning uses stock before it suggests new supply.
9Safety Lead TimeOptionalOptionalBuffer days; shows as slack on the board.
10Item Tracking CodeSame in every companySame in every companyLot advice needs lot tracking. Keep the base unit of measure the same everywhere too.

Set Up Work Centers, Machine Centers & Calendars

Only production companies need capacity. Production orders schedule their operations on machine centers; the planning board compares the load of those operations with the calendar.

  1. Choose the Search (Tell me) icon, enter Work Centers, and create a work center per production line.

  2. Enter Machine Centers and create a machine center per machine, with Work Center No. of its line.

  3. On each card choose Calculate Calendar, from today to at least the plan horizon (90 days by default).

  4. Use the machine centers in the routings of the produced items, and certify the routings.



Work Center Card
FieldDescriptionDefault
1Work Center Group Code REQUIREDGroups work centers for reporting. Business Central requires it before a calendar can be calculated.
2Unit of Measure CodeTime unit of capacity and run times.
3CapacityHow many machines or people work in parallel.1
4EfficiencyPercentage of the time that is productive.100
5Shop Calendar Code REQUIREDWorking days and hours. Capacity on the board comes from it.
6Calculate Calendar REQUIREDAction on the work center and machine center cards. Creates the calendar entries for a period. No calendar entries = zero capacity on the board and in Capacity Load.

Important: Calendar entries run out. Recalculate the calendars regularly (for example monthly, from the job queue), otherwise capacity drops to zero at the end of the period and every operation after it looks overloaded.

Note: A machine that two companies use, such as one bonding line in a shared building, is set up as a machine center in each company. Shared Machines then joins them.

Set Up Manufacturing & the Planning Worksheet

Chain Planning runs Calculate Regenerative Plan and Carry Out Action Message in each company. These standard settings decide how that plan is calculated.

  1. Choose the Search (Tell me) icon, enter Manufacturing Setup, and fill in the fields below.

  2. Enter Planning Worksheet. In Name, create a batch such as DGB-APS — one per company, used only by Chain Planning.



Manufacturing Setup

FieldDescriptionDefault
Planning (Manufacturing Setup)
1Combined MPS/MRP CalculationPlans finished items and components in one run. Chain Planning calculates the plan this way.On
2Components at LocationLocation of components when the item has none. Match it with where stock is.
3Default Safety Lead TimeBuffer between the need date and the due date of supply.1D
4Current Production ForecastLeave blank unless you plan on forecast; the apps plan on orders.
5Default Dampener %Tolerance before planning suggests a change. Keep 0 so every change shows up.0
Numbering & Times
6Firm Planned Order Nos. REQUIREDNumber series for firm planned production orders that Carry Out creates.
7Normal Starting / Ending TimeDefault times of a production day.
Planning Worksheet
8Worksheet template and batch REQUIREDA template of type Planning and a batch of its own in every company. Chain Planning recalculates this batch each run, so planners’ own batches stay untouched.

Part B - Centralised Production Planning

This lets a planning company see stock and production capacity in every production company, and source planning lines from the right plant through intercompany.

Mark the Production Companies

Each plant says that it is a plant. Planning companies then find it automatically.

To mark a production company:

  1. Sign in to the production company.

  2. Choose the Search (Tell me) icon, enter Company Information, and then choose the related link.

  3. On the General FastTab, in the Centralised Production Planning group, fill in the fields.

  4. Repeat in every production company. In planning (sales) companies, leave Is Production Company off.



Company Information
FieldDescriptionDefault
1Company CodeA short code for the company. Planning companies show it next to the company name in availability views.
2Is Production Company REQUIREDMarks the company as a plant that manufactures for the group. Discover Production Companies in planning companies finds the plants by this flag, and the availability FactBox is hidden in production companies.Off

Note: A company can be a production company and still plan, as level 2 does: it produces mats and sources carpet from level 3. Set Is Production Company on, and also set up CPP Setup there with level 3 as its production company.

Use the Guided Setup

The guide Set Up Centralised Production Planning does the next two pages for you in about five minutes. Run it in every planning company; in a production company it only sets the flag of the previous page.

  1. Choose the Search (Tell me) icon, enter Assisted Setup, and choose Set Up Centralised Production Planning. You can also start it from Centralised Production Planning Setup with Set Up Production Planning (Guided).

  2. Follow the steps in the table. Choose Next after each step and Finish at the end.



Set Up Centralised Production Planning
StepWhat you doSets
1Before you startCheck the prerequisites: IC partners, IC vendors, same item numbers.—
2What does this company do?Production company or planning company, and the Company Code.Company Information
3Production companiesFind Production Companies adds every plant and maps its IC vendor from the IC partner code. Check the list and the priorities.Production companies
4QuantitiesAvailable or total inventory, sub-assemblies, BOM levels.Calculation fields
5Items in stepSame Item No. or MDS Master Data Sync.Item Link Provider
6You’re all setFinish, then set your role to Production Planner (Group).—

You can run the guide again at any time; it only adds what is missing.

Actions on Centralised Production Planning Setup

ActionWhat it does
Discover Production CompaniesAdds every company marked as a production company and maps its IC vendor.
Set Up Production Planning (Guided)Opens this guided setup.
Production ReadinessChecks that items, BOMs, components and routings exist in every plant.
Production Company AvailabilityExports stock, available quantity and Qty. Able to Make per plant to Excel.

Centralised Production Planning Setup

One setup page per planning company. The top half decides how quantities are calculated; the bottom half lists the production companies (next page).

  1. In a planning company (level 1, or level 2 when it sources from level 3), choose the Search (Tell me) icon, enter Centralised Production Planning Setup, and then choose the related link.

  2. Fill in the fields. The defaults suit most companies.



Centralised Production Planning Setup
FieldDescriptionDefault
Calculation
1Use Available InventoryCalculates with available inventory (inventory minus quantities reserved against it) instead of total inventory. Recommended: On, so stock promised to other orders is not offered twice.On
2Include Sub-Assembly CapacityQty. Able to Make also counts sub-assemblies the plant can still produce from stock, not only sub-assemblies already in stock. More realistic for multi-level BOMs.On
3Max. BOM LevelsHow many production BOM levels are exploded. Also protects against circular BOMs. Raise it only for very deep structures.10
4Default Location FilterLocations that count as stock in production companies that have no filter of their own, for example MAIN|FG. Blank = all locations.Blank
Item Link
5Item Link ProviderHow items are matched across companies. Same Item No. (manual): you create items with the same number everywhere. MDS Master Data Sync (needs the MDS Connector): missing items, BOMs and routings can be requested from the master.Same Item No.
Planning Worksheet
6Show FactBox in Planning WorksheetShows the Production Company Availability FactBox next to the planning lines in this company.On
7Calculate Qty. Able to Make in FactBoxCalculates Qty. Able to Make whenever you move to another line. Turn off for very deep BOMs if the FactBox feels slow; the value is still calculated when you drill down.On

Add the Production Companies

The Production Companies part of the setup page lists the plants this company can see and source from.

To add production companies:

  1. On Centralised Production Planning Setup, choose Discover Production Companies. Every company with Is Production Company is added, and its IC vendor is found from the IC partner code.

  2. Check IC Vendor No. on each line; fill it in where it is blank.

  3. Set Priority and, if needed, Location Filter.



Production Companies
FieldDescriptionDefault
1Company Name REQUIREDThe Business Central company that manufactures the items.
2Display NameName shown in the FactBox, on the report and in the company list.Company name
3EnabledIncludes the company in availability and sourcing. Turn off to stop sourcing from a plant without deleting it.On
4PrioritySourcing priority. Auto-Source prefers lower numbers when several plants can cover the demand.0
5IC Vendor No. REQUIREDThe vendor in this company that represents the plant. Planning lines sourced from the plant get this vendor, so Carry Out creates an intercompany purchase order.
6IC Partner CodeThe IC partner code of that vendor. Blank = purchase orders to the vendor are not sent through intercompany.From vendor
7Location FilterLocations in the plant that count as stock, for example MAIN|FG. Blank = Default Location Filter, or all locations.Blank

Note: In a three-level chain, the sales company lists only level 2. Level 3 is listed in level 2’s own CPP Setup.

Sourcing works only when the plant knows the item: the item, its production BOM, every component and the routing must exist there. Production Readiness checks this before you send work to a plant.

Item Link Provider

ValueWhen to useWhat happens when something is missing
Same Item No. (manual)Items are created by hand, or by another tool, with the same number in every company.Readiness shows what is missing; you create it in the plant.
MDS Master Data SyncMDS Master Data Sync and the MDS Connector are installed.Readiness requests the missing item, BOM or routing from the MDS master with one action.

To check readiness:

  1. On the planning worksheet, select lines and choose Production Company › Check Production Readiness. Or open Production Readiness from the setup page or the role center.

  2. Review the lines. A red status means the plant cannot produce the item yet.

  3. Create the missing records, or request them from the master (MDS).



Production Readiness
ColumnMeaning
1Item No.The item on the planning line.
2Production CompanyThe plant checked.
3 — 6Item, Production BOM, Components, RoutingWhether each exists in the plant, and whether the BOM and routing are certified.
7StatusReady, or what is missing.

What CPP Adds to the Planning Worksheet

After setup, planners work on the standard Planning Worksheet. CPP adds one field, a FactBox and a group of actions.



Production Worksheet
ElementWhat it does
1Source Production Company (field)The plant the line is sourced from. Set by the two sourcing actions together with the plant’s IC vendor.
2Production Company Availability (FactBox)Per plant: inventory, available quantity and Qty. Able to Make for the item of the current line. Controlled by Show FactBox.
3Qty. Able to MakeHow many the plant can make from its component stock (and sub-assemblies, if set up). Drill down for the BOM explosion.
4Source from Production CompanyChoose a plant for the current line. The line becomes a purchase from the plant’s IC vendor.
5Auto-Source Selected LinesPicks the highest-priority plant that covers the quantity from stock, then from stock plus what it can make.
Split LineSplits a line into several with the same total, for example over two plants or batches.
Check Production Readiness, Production Company Availability, Production Planning SetupSee Production Readiness and CPP Setup.

Note: With Advanced Planning, Chain Planning runs the sourcing step for you (Source from Group) in every company, in chain order.

Part C - Advanced Planning

The group planning board, Chain Planning across companies, shared machines and board views. Advanced Planning Setup is per company; the planning group, shared machines and board views are shared by all companies.

Advanced Planning Setup: Planning Board

The Planning Board FastTab sets how the board opens in this company. Users can change most of it on the board itself.

  1. Choose the Search (Tell me) icon, enter Advanced Planning Setup, and then choose the related link. The page is created with defaults when the app is installed.

  2. Fill in the Planning Board FastTab.

  3. Repeat in every company where people open the board.



Advanced Planning Setup - Planning Board
FieldDescriptionDefault
1Days BackHow many days before the work date the board shows by default. Late orders older than this are still found with Go to orders.7
2Days AheadHow many days after the work date the board shows. Match it roughly with your order book.60
3Include Planning SuggestionsShows planning worksheet lines as dashed bars and uses them as supply in pegging. Turn off to see only real orders.On
4Show OperationsShows the operations (routing lines) under each production order. Needed for the machine view and capacity load.On
5Auto Refresh (Seconds)Refreshes the board on its own, for example 300 on a wall screen. 0 = only when you choose Refresh.0
6Max. Trace LevelsHow many supply levels Supply Chain Trace follows across companies.10
7Warn When No Single Lot CoversWarns on the board and in the trace when no single lot of a lot-tracked component covers the need, for example to keep one colour per job.On
8Default Board ViewThe board view the planning board opens with. Use it to show only one product line.Blank

Advanced Planning Setup: Chain Planning

Chain Planning plans every company of the group in chain order with one action. In each company it runs these steps, using the settings on this FastTab:

StepWhat happens
1 Accept IC InboxAccepts incoming IC orders, so demand from the level above is there.
2 Calculate PlanCalculate Regenerative Plan on the batch, for the plan horizon.
3 Source from GroupCPP sourcing: lines for items made in a plant become IC purchases from that plant.
4 Carry OutAccepts and carries out the action messages: orders are created and changed.
5 Send IC OrdersSends the new IC purchase orders to the next company.


Advanced Planning Setup - Chain Planning
FieldDescriptionDefault
1Planning Worksheet Template REQUIREDThe planning worksheet template (type Planning) Chain Planning uses in this company.
2Planning Worksheet Batch REQUIREDThe batch Chain Planning calculates and carries out. Use a batch of its own.
3Plan Horizon (Days)How many days ahead from the work date the plan is calculated. Longer = slower; shorter = late orders beyond the horizon are not planned.90
4Carry Out AutomaticallyCarries out the action messages (creates and changes orders) in this company. Turn off to review the worksheet before anything is created; Chain Planning then stops after Calculate Plan in this company.On
5Send IC Orders AutomaticallySends new intercompany purchase orders to the partner right away, so the next company in the chain has the demand for its own run.On

Important: Fill in template and batch in every company of the planning group. A company without them fails at step 2, and the companies below it get no demand.

Note: Chain Planning plans as of your work date, in every company of the group.

Advanced Planning Setup: Priorities & Scheduling

These rules decide how the board shares stock and machine time between orders, and how far it may move work on its own.

  1. Choose the Search (Tell me) icon, enter Advanced Planning Setup, and open the Priorities and Scheduling FastTab.

  2. Fill in the fields as described in the table.



Advanced Planning Setup - Priorities & Scheduling
FieldDescriptionDefault
1Allocate Stock by PriorityFree stock and existing supply go to Rush and High orders first, then Normal and Low, each by date. When off, they go to orders by date only: first come, first served. Reserved stock always stays with its order.On
2Frozen Zone (Days)Orders and operations that start within this many days from today are frozen: Push Dependent Orders, Expedite and sequencing leave them where they are. You can still move them yourself. Use it for work that is already prepared on the shop floor.0
3Skip Days Without CapacitySequencing and promise dates skip days on which a machine has no capacity in its calendar: weekends, holidays, a breakdown.On
4Safety Days in Promise DateDays added to a promise date as a buffer between the end of production and shipment.1

Planning Priority on Orders

The sales order and the production order get a field Planning Priority on the General FastTab: Rush, High, Normal (default) or Low. Sales or customer service set it on the sales order; planners can also set it on the board. A production order on Normal takes the most urgent priority of the customer orders it supplies.

Tip: Agree with sales who may set Rush. When every order is rush, none is: keep it for the few orders that must go first.

Set Up the Planning Group

The planning group lists every company that the board shows and Chain Planning covers. It is shared: one list for all companies.

  1. Choose the Search (Tell me) icon, enter Planning Group, and then choose the related link.

  2. Choose Add Production Companies. It adds the current company (level 1, Sales) and the production companies of CPP Setup (level 2, Production).

  3. Correct the levels: in a three-level chain, set the carpet plant to 3.

  4. Set Short Name and Board Colour for each company.



Planning Group
FieldDescriptionDefault
1Company Name REQUIREDA company that takes part in group planning.
2Display NameName shown on the board and in the trace.Company name
3Short NameShort label on bars, chips and row headers, for example SALES, MATS, CARPET. Keep it under 8 characters.Company name
4RoleSales / Trading, Production, or Sales and Production. Shown on the board; helps planners read the chain.Sales
5Chain Level REQUIREDPosition in the supply chain. Level 1 receives customer orders, level 2 supplies level 1, and so on. Chain Planning runs the companies in this order.1
6EnabledShows the company on the board and includes it in Chain Planning.On
7Board ColourColour of this company on the board, for example #2F6FD0 for blue. Choose clearly different colours.Automatic

Tip: Two companies can share a level when they both supply the level above. Chain Planning runs them one after the other.

Set Up Shared Machines

When companies share a building and a machine, each company has its own machine center for it, and each sees only its own load. A shared machine joins them: the board shows the combined load on one row, and Capacity Conflicts finds clashes between companies.

  1. Choose the Search (Tell me) icon, enter Shared Machines, and then choose the related link.

  2. Create a line per shared machine.

  3. In Company Machines, add one line per company that uses it, and mark one as Owner.



Shared Machines
FieldDescriptionDefault
Shared machine
1Code REQUIREDCode of the shared machine or line.
2DescriptionFree text.
3MembersHow many company machine centers or work centers represent it. Calculated.
Company Machines (members)
4Company Name REQUIREDThe company whose work center or machine center represents the shared machine.
5Capacity Type REQUIREDWork Center or Machine Center.Work Center
6No. REQUIREDThe work center or machine center in that company.
7Owner (Capacity) REQUIREDThis member’s calendar is the real capacity of the machine. The load of all members is compared with it. Set exactly one owner.Off

Note: Optional. Without shared machines, the board shows each company’s machine centers on their own rows.

Set Up Board Views

A board view is a saved way of looking at the board: which companies, items and machines, which period and what to show. Views are shared by all companies. Planners choose a view in the View field on the board: Default Board View sets the one it opens with.

  1. Choose the Search (Tell me) icon, enter Board Views, and then choose the related link.

  2. Create a line per view. The fields are described here and on the next page.



Board Views
FieldDescriptionDefault
1Code REQUIREDCode of the view.
2DescriptionWhat the view is for.
3View TypeOrders by company: one group per company. Machines and work centers: one row per machine with its load strip. Customer orders and their supply: each customer order with its whole supply chain under it.Orders by company
4Company FilterGroup companies the view shows, for example SALES CO|MAT PLANT. Blank = all.Blank
5Item FilterItems the view shows. Use it to show only one product line or customer range.Blank
6Work/Machine Center FilterWork centers, machine centers or shared machines the view shows. Mainly for the machine view.Blank
7Days BackDays before the work date.7

Fields 8—14 of the Board Views list decide the period and what the board draws.

FieldDescriptionDefault
8Days AheadDays after the work date.60
9ZoomTime scale the view opens with: Day, Week or Month.Week
10Show DependenciesDraws arrows between supplying and consuming orders.On
11Only Late or At RiskShows only orders that are late, or at risk because something they depend on is late. Good for a daily exceptions view.Off
12Show Planning SuggestionsShows planning worksheet lines as dashed bars.On
13Show OperationsShows operations under production orders.On
14Auto Refresh (Seconds)Refreshes the view on its own, for example 300 on a wall screen. 0 = manual.0

Recommended Views

CodeView TypeFilters and optionsFor
GROUPOrders by companyNo filtersThe planning office: everything, grouped by company.
ORDERSCustomer orders and their supplyItem filter on your product lineSales and customer service: each customer order with its supply, red when late.
MACHINESMachines and work centersResource filter on the line; Zoom Day; Auto Refresh 300Wall screen on the shop floor.
LATEOrders by companyOnly Late or At Risk; Days Back 30Daily exception list.

Tip: To focus on one product line, create a view with an Item Filter and make it the Default Board View. All other orders in the companies stay out of sight.

Where the Apps Add Actions

These actions need no setup. Use this table to find them, and to check that every planner sees them.

PageActionOpens
Role center Production Planner (Group)
Role CenterPlanning Board (part and action), Run Chain PlanningThe board; Chain Planning for the group.
Role Center > Advanced PlanningChain Planning Runs, Shared Machines, Capacity Conflicts, Reschedule Requests, Board Views, Planning Group, Advanced Planning SetupThe pages of this part.
Standard pages
Sales OrderSupply Chain Trace, Show on Planning BoardTrace of the order across companies; the board focused on the order.
Sales Order Subform (lines)Supply Chain TraceTrace of the selected line.
Firm Planned and Released Prod. OrderSupply Chain Trace, Show on Planning BoardWhere the order’s output goes and what it needs.
Item CardLot AvailabilityLots in every company and single-lot advice.
Planning WorksheetAdvanced Planning › Planning Board, Run Chain PlanningBoard and Chain Planning from the worksheet.
Planning WorksheetProduction Company group (CPP)
Centralised Production Planning SetupMDS Setup, MDS Sync Log, Link Planning Items NowOnly with the MDS Connector.

Pages Without Setup Fields

These pages show results and need no setup: Chain Planning Runs and its steps, Reschedule Requests, Capacity Load, Capacity Conflicts, Supply Chain Trace, Lot Availability, What-If Changes. They are described in the user guide.

Verify the Setup

Three checks prove that the setup works from end to end. Run them in the level 1 company with one sales order for a produced item.

Production Readiness

Open Production Readiness and check that every item is Ready in every plant.

Run Chain Planning

  1. Choose Run Chain Planning on the role center and confirm.

  2. In Chain Planning Runs, wait until the run is Completed: five steps per company, all green.



Chain Planning Runs
If a step failsCheck
Accept IC InboxIC partner Inbox Type and Inbox Details; the IC customer exists.
Calculate PlanTemplate and batch in Advanced Planning Setup; item Reordering Policy.
Source from Group / Carry OutIC Vendor No.; number series in Manufacturing Setup.
Send IC OrdersIC Partner Code on the vendor; Intercompany Setup of the partner.

Planning Board

Open the Planning Board with the Customer orders and their supply view. The sales order shows its IC orders and production orders in the other companies underneath, linked by arrows.

Part D - Optional Apps & Checklist

The optional MDS Connecto, the Production Planning Board for a single company, and a checklist to sign off the setup company by company.

Set Up the MDS Connector (Optional)

With MDS Master Data Sync, one master company owns items, BOMs and routings and sends them to the other companies. The connector lets CPP ask the master to resend what a plant is missing.

  1. Make sure MDS Master Data Sync is set up, with a master company and the receiving companies, and that the MDS Connector is installed.

  2. On Centralised Production Planning Setup, set Item Link Provider to MDS Master Data Sync.

  3. Check the MDS Master field: it shows how this company reaches the master.

  4. Optional: ask your administrator to run Link Planning Items Now every night from the job queue.



Centralised Production Planning Setup
FieldDescriptionDefault
1Item Link Provider REQUIREDMDS Master Data Sync — value added by the connector.Same Item No.
2MDS MasterRead-only. How this company reaches the MDS master that is asked to resend missing items, BOMs and routings.
3MDS Setup (action)Opens MDS Master Data Sync setup for this company.
4MDS Sync Log (action)MDS service calls and sync events, including resend requests from CPP.
5Link Planning Items Now (action)Checks every item on the planning worksheets against the plants and requests anything missing. It can also run every night on its own.

Caution: Exclude the per-company planning fields from the MDS item sync (Replenishment System, Vendor No., Manufacturing Policy, Routing No., Production BOM No., Reordering Policy). Otherwise MDS overwrites the role of the item in each company.

Production Planning Board for One Company

Companies that plan production in one company can use d365 Production Planning Board on its own. It is the same board with the same functions as Part E, without anything that spans companies.

FunctionAdvanced Planning (group)Production Planning Board (one company)
Board views: customer orders, orders, machinesYes, all companiesYes
Move orders and operations, impact on linked ordersYes, across companiesYes
Priorities, Expedite, Sequence machinesYesYes
Move operations to another machineYesYes
Shortages, Order Coverage, Promise datesYesYes
Frozen zone, started workYesYes
Chain Planning, intercompany linksYesNo
Planning group, shared machinesYesNo
Needs Centralised Production PlanningYesNo — no other app needed

To set it up:

  1. Your administrator installs d365 Production Planning Board and gives planners the permission set DGB PPB.

  2. Choose the Search (Tell me) icon, enter Production Planning Board Setup: the same fields as the planning board FastTab and priorities and scheduling.

  3. Create board views if you like, and open Production Planning Board from Tell me or the Production Planner home page.

Note: Prerequisites are the same as Part A for one company: items with routings and production BOMs, machine centers with calendars, and a planning worksheet.

Setup Checklist Per Company

Print this page and tick each line per company. ✔ = needed in that company. You can click on the link under the Page column to get to the setup information.

SetupLevel 1 SalesLevel 2 PlantLevel 3 PlantPage
Business Central
Intercompany Setup: IC Partner Code, Inbox Type Database☐☐☐Intercompany
IC partner for each neighbour in the chain☐☐☐IC partners
IC vendor for the level below☐☐—IC vendors
IC customer for the level above—☐☐IC customers
Items with the same numbers; replenishment per role☐☐☐Items
Certified BOMs and routings—☐☐Items
Work centers, machine centers, calendars calculated—☐☐Capacity
Manufacturing Setup; planning batch DGB-APS☐☐☐Manufacturing
Centralised Production Planning
Company Information: Is Production Company, Company Code—☐☐Company Info
CPP Setup: calculation and item link☐☐—CPP Setup
Production companies with IC Vendor No.☐☐—Prod. companies
Advanced Planning
Advanced Planning Setup: board defaults☐☐☐APS Setup
Advanced Planning Setup: template, batch, horizon☐☐☐Chain Planning
Planning Group (once): levels 1—3☐Planning Group
Shared machines (once, optional)☐Shared Machines
Board views and default view (once)☐Board Views
Users
Permission sets in every company☐☐☐Permissions
Role Production Planner (Group)☐☐☐Role center
Verified: readiness, chain run, board☐Verify

Part E - Using the Planning Board

The Planning Board shows the orders of every company in the group on one timeline: customer orders, the intercompany orders between the companies, production orders with their operations, and purchases. You see which orders are late, why, and what happens when you change a date.

Open the Board & Choose What To See

  1. On the home page, choose Planning Board. You can also open it from a sales order, a production order or the planning worksheet with Show on Planning Board; the board then opens on that order.

  2. In View, choose a saved view, and in Show, choose how to group the orders.

  3. Set Move Supply with Order and Push Dependent Orders before you move anything.



Planning Board
FieldDescriptionDefault
1ViewThe saved board view: which companies, items and dates. Blank = the default view.Default view
2ShowOrders by company, Machines and work centers, or Customer orders and their supply.From the view
3Move Supply with OrderWhen you move an order, every order that supplies it moves by the same number of days, in every company.On
4Push Dependent OrdersWhen you move an order later, the orders that need it are pushed out by the delay, up to the customer order.On
5SelectedThe order or operation you clicked.
6What-If ChangesHow many orders you moved. Nothing is saved until you choose Apply Changes.
7LoadedWhen the board was loaded, and how many orders it holds.
MenuActions
BoardRefresh, Apply Changes, Discard Changes, Show Changes, Order Coverage
Selected OrderChange Date…, Supply Chain Trace, Open Document, Lot Availability, Set Priority…, Expedite Order…, Promise Date…
CapacityMove to Machine…, Sequence All Machines, Level Load Machine, Capacity Conflicts, Capacity Load
PlanRun Chain Planning, Chain Planning Runs, Reschedule Log, and the setup pages

Find Orders: Toolbar and Filters

The toolbar at the top of the board moves the timeline and filters the orders. Under it, one chip per company hides or shows that company.



Planning Board - Toolbar
ButtonWhat it does
1Day, Week, MonthTime scale of the timeline.
2TodayScrolls to the work date. A vertical blue line marks it.
3Go to ordersScrolls to where the orders are, for example when they are far from today.
4Next late ▶Selects the next late order and scrolls to it.
5Expand all / Collapse allOpens or closes what is under every order. Use ▸ / ▾ in front of one order for that order only.
6LinksShows or hides the arrows between supplying and consuming orders.
7Late onlyOnly late (red) and at-risk (amber) orders.
8SearchType an order number or item; matching orders stay, with what is under them.
9? HelpA short help panel on the board itself.
10RefreshReloads the board from all companies. Moves you have not applied are lost.
11Full screenUses the whole screen, for example on a wall monitor.
12, 13Company chips, Clear filtersHide a company; switch every filter off in one click.

Read the Board

With Show = Customer orders and their supply, each customer order has its whole supply chain under it, across the companies. This is the example used on the next pages.



Planning Board - One Customer Order
You seeMeaning
1Order rowIts coloured left edge shows the company (colour from the planning group).
2Indent and ▸ / ▾What is under an order supplies it: the IC order, the production order, its operations and components.
3Bar of a customer orderShipment date. Sales, intercompany, production and purchase orders each have their own colour.
4Bar of a production orderFrom starting to ending date; its operations are underneath.
5Dashed grey barA planning worksheet suggestion, not an order yet.
Red outlineLate because of its own dates: it is ready after it is needed.
Amber outlineAt risk: its own dates are fine, but something it waits for is late.
Thin red line with +N dHow many days late the order will be ready.
Dashed blue outlineYou moved it; not saved yet.
ShowUse it to
Customer orders and their supplyFollow one customer order through every company. Orders not linked to a customer order are in a group at the end.
Orders by companySee all orders of each company together.
Machines and work centersSee operations per machine, with the daily load.

Select an Order

Click an order’s name, its bar or its red line. A blue strip above the board shows the order and what you can do with it.



Planning Board - Selected Order
ButtonWhat it does
1Change date…Asks for the new date, and whether supply and dependent orders move too.
2, 3◀ 1 day, 1 day ▶Moves the order one day earlier or later.
4TraceFollows the supply of the order through every company.
5OpenOpens the document. Orders of another company open in a new browser tab, in that company.
6LotsFree lots of the item or its lot-tracked components, in every company.
7×Clears the selection (Esc).
8 — 10Priority…, Expedite…, Promise date…For an operation, Machine… appears instead.

Other Ways to Move an Order

Do thisTo
Drag the barMove the order to another date.
Drag the right edge of a barMake a production order or operation longer or shorter.
Left / right arrow keyMove one day earlier / later.
Shift + left / right arrowMove one week.
Enter / EscOpen the Change Date dialog / clear the selection.

Note: Every move is a what-if. The board shows the effect at once, but nothing is saved in Business Central until you choose Apply Changes.

Change the Date of a Production Order

Example: the bonding line at MAT PLANT needs three more days for production order FP-4004.

  1. Open the board with Show = Customer orders and their supply, and expand SO-1004.

  2. Click FP-4004 and choose Change date… in the blue strip.

  3. Enter the New Date, three days later. Choose whether the supply moves and whether the orders that need it are pushed.

  4. Choose OK. The board shows the result at once; see the next page.

  5. Choose Apply Changes to save it, or Discard Changes to undo.



Change Date
FieldDescriptionDefault
1OrderThe order you selected.
2Current DateThe current date: end date of a production order or operation, shipment date of a sales order, receipt date of a purchase.
3New DateThe date to move to.
4Days MovedHow many days it moves. Negative = earlier.
5Move Its Supply TooEverything that supplies this order moves by the same number of days: component purchases, IC orders and production orders in other companies. Stock does not move.Board setting
6Push Dependent OrdersWhen the order moves later, the orders that need it are pushed out by exactly the delay, up to the customer order.Board setting

Tip: The two switches start with the values of Move Supply with Order and Push Dependent Orders above the board, so set those once for your way of working.

How a Change Reaches the Linked Orders

The same move of FP-4004, three days later, with Push Dependent Orders off and on. The board works out the effect on every linked order in every company.

Push Dependent Orders off: the board shows who is affected



Planning Board — Production order moved, not pushed
OrderCompanyWhat you see
1FP-4004 production order and its operationsMAT PLANTDashed blue: moved three days.
2SO-3004 IC sales orderMAT PLANTAmber: its production order is now late.
3PO-2004 IC purchase orderSALES COAmber: its supplier in MAT PLANT is late.
4SO-1004 customer orderSALES CORed, +3 d: the hotel gets it three days late.

Push Dependent Orders on: the linked orders move with it



Planning Board — Production order moved and pushed

SO-3004 1 and its other half PO-2004 2 move three days, and so does the shipment date of SO-1004 3 . After Apply Changes, the new dates are in all three documents. Tell the customer about the new date.

Change Sales & Purchase Dates

Any order can move: customer orders, intercompany orders, production orders, operations and purchases. Three rules decide what moves with it.

RuleWhenWhat moves
1. The other half of an intercompany orderAlwaysAn IC purchase order and its IC sales order in the other company are one delivery: move one and the other follows.
2. Move Supply with OrderSwitch onEverything under the order — IC orders, production orders, operations, purchases — moves by the same number of days, in every company.
3. Push Dependent OrdersSwitch on, and the order moves laterEverything above the order that needs it is pushed out by exactly the delay, up to the customer order.

Examples

You moveSwitchesResult
Customer order SO-1004 5 days earlier (the hotel wants it sooner)Supply offOnly SO-1004 moves. It turns red: its supply now arrives too late. Shows that the request cannot be met as is.
Customer order SO-1004 5 days earlierSupply onThe whole chain moves five days earlier in all three companies. Red where an order would have to start before today.
Carpet purchase PO-5004 4 days later (supplier delay)Push offPO-5004 and its other half SO-6004 move. FP-4004 turns amber, then SO-3004 and PO-2004, and SO-1004 turns red.
Carpet purchase PO-5004 4 days laterPush onFP-4004 and everything above it are pushed out by four days, up to the new shipment date of SO-1004.
Operation 10 on MC-BOND 1 day laterPush onThe operation moves; the production order ends a day later, and the orders above it are pushed by one day.


Planning Board — Customer order earlier with its supply

1 SO-1004 moved, 2 its supply moved with it, 3 the carpet production order would have to start before today: red. That tells you how much earlier is possible.

Apply or Discard Your Changes

Moves on the board are what-if until you apply them. What-If Changes above the board shows how many orders you moved, and the board shows a WHAT-IF badge.

Check, Apply or Undo

  1. Choose Board › Show Changes to see every moved order with its old and new dates.

  2. To undo everything, choose Discard Changes. Refresh also discards.

  3. To save, choose Apply Changes, and then Yes. Each change is written in the company that owns the order.

  4. Answer Yes to run Chain Planning, so every company’s planning follows the new dates.



What-If Changes

What Apply Changes Writes:

OrderField that changes
Customer and IC sales orderShipment Date on the line
IC and normal purchase orderExpected Receipt Date on the line
Production orderStarting Date-Time; Business Central reschedules the operations
OperationStarting and ending date-time of the routing line
Planning worksheet lineDue Date

Note: Released orders are reopened, changed and released again for you. Choose Plan > Reschedule Log to see every change and whether it was saved; a failed line shows why, for example a document waiting for approval.

Trace the Supply & Check Lots

Supply Chain Trace answers “why is this order late?”. It follows an order down through every order that supplies it, across the companies. Open it from the board (Trace), or from a sales or production order.



Supply Chain Trace
ColumnMeaning
1Level0 is the order you traced; 1 supplies it, 2 supplies 1, and so on.
2CompanyWhere the order is.
3, 4Needed By, ReadyWhen the order above needs it, and when it is ready.
5LateReady after it is needed. The lowest late line is the cause.
6LotsFor lot-tracked items: a warning when no single lot covers the need, and the suggested lot.

Lot Availability

From the board (Lots) or the item card: the free lots of an item, or of its lot-tracked components, in every company, with an Advice line, for example to use one lot per job so the colour stays the same.

Check Capacity

Business Central plans production as if machines have unlimited hours, so two orders can sit on the same machine at the same time. The board shows where capacity runs out, so you can decide which orders will be late.

WhereWhat it tells you
Show = Machines and work centersOne row per machine with its operations, and a load strip under it: green under 80 %, amber from 80 to 100 %, red above. A shared machine shows the operations of every company on one row.
Capacity > Capacity LoadPer machine and day: capacity hours from the calendar, load hours from all companies, load %, and whether it is overloaded. Includes your what-if moves.
Capacity > Capacity ConflictsEvery pair of operations on the same machine at the same time, with the overlap in hours. Cross-Company = clash between two companies on a shared machine.
Capacity > Level Load MachineSelect an operation first. Lines up all operations on its machine one after the other, so nothing overlaps. Operations pushed past their date turn their orders red, up to the customer order.


Capacity Load

When a machine is overloaded:

  • Level Load Machine shows the realistic dates. Keep it if the late orders are acceptable, and choose Apply Changes.

  • Move an order to another day with Change date…, or move the customer order later and tell the customer.

  • Add capacity: an extra shift in the machine’s calendar. The board shows the new capacity after Refresh.

  • Discard Changes if you only wanted to see the effect.

Plan the Whole Chain

Run Chain Planning plans every company in chain order with one action: new customer orders become intercompany orders and production orders in all companies. Run it after new orders, and after Apply Changes.

  1. Choose Run Chain Planning on the home page, the board (Plan) or the planning worksheet, and confirm.

  2. Open Chain Planning Runs to follow it. Each company runs five steps, level 1 first.

  3. When the run is Completed, choose Refresh on the board.

StepWhat happens in the company
Accept IC InboxOrders from the level above are accepted.
Calculate PlanThe planning worksheet is calculated.
Source from GroupLines for items made in a plant become purchases from that plant.
Carry OutOrders are created and changed.
Send IC OrdersNew intercompany purchase orders go to the next company.
StatusMeaning and what to do
RunningBusy. Choose Refresh on Chain Planning Runs.
CompletedAll steps done in all companies.
FailedOpen the run: the failed step shows the message. Fix the cause (see Verify the setup) and run again.

Tip: Chain Planning plans as of your work date. Check the work date in My Settings before you run it.

Priorities & Rush Orders

Not every order is equal. A key customer’s urgent order should get stock, supply and machine time before a stock replenishment that can wait. The planning priority tells the board which orders go first.

PriorityBadgeMeaning
RushRUSHGoes before everything else: first pick of stock and supply, first on the machines.
HighHIGHBefore Normal and Low orders.
Normal—The default. Orders are served by date.
LowLOWServed last, for example stock replenishment or orders the customer can wait for.

How priority flows through the plan:

  • A customer order has its own priority (field Planning Priority on the sales order).

  • The production orders, purchases and intercompany orders that supply it take the same priority, down the chain. A production order that serves a rush and a normal order is rush.

  • Operations take the priority of their production order, so a rush job goes first on every machine when you sequence.

  • In the Customer orders view, rush orders are listed at the top of each company.

To change a priority on the board:

  1. Select a customer order or a production order, and choose Priority… in the blue strip (or Set Priority…).

  2. Choose Rush, High, Normal or Low.

  3. The board allocates stock and supply again, most urgent first, and shows the effect: an order that gets the stock turns green or on time, an order that loses it can turn SHORT or late.

  4. Choose Apply Changes to write the priority on the order, or Discard Changes.

Note: Reserved stock is never taken from its order. If a rush order needs stock that is reserved for another order, the trace shows it; remove the reservation on that order first.

Expedite an Order: Who gains, who waits

Expedite Order… does what a planner does for a rush order, in one step, as a what-if: priority, stock, supply, machines. Then it lists every customer order whose date changed, so you see the price of the rush before you commit.

  1. Select the customer order (or its production order) and choose Expedite….

  2. Choose the steps in the dialog and choose OK.

  3. Read the summary and the list Effect on Customer Orders: the expedited order at the top, then the orders that are earlier (green) or later (red).

  4. Keep it with Apply Changes, or undo it with Discard Changes.



Expedite Order
FieldDescriptionDefault
1New PriorityThe priority the order gets. Rush goes before everything else.Rush
2Give It Stock FirstFree stock and existing supply go to this order before orders with a lower priority, even if they are due earlier.On
3Pull Its Supply EarlierIts production orders and purchases move earlier by the days it is late, but not before today and not in the frozen zone.On
4Put It First on the MachinesIts operations go first on every machine they use; the other operations follow by priority and date.On
5Move the Delayed Orders OutCustomer orders delayed by this get new shipment dates. When off, they keep their dates and show red, so you decide per order.Off


Effect on Customer Orders

Move Work Between Machines

When a machine is overloaded or down, move operations to another machine of the same work center, or let the board plan each machine one job at a time.

Move one operation

  1. Set Show to Machines and work centers. Every machine of a work center has a row, also the idle ones.

  2. Drag the operation up or down onto another machine row. The bar turns green over a machine it may move to, red over one it may not.

  3. Or select the operation and choose Machine…: a list shows each machine of the work center with the duration there, its capacity that day and the hours already planned.

  4. The duration follows the new machine’s efficiency and capacity: a machine at 125 % does the same work in 80 % of the time.

  5. Apply Changes writes the new machine on the routing line of the production order; Business Central recalculates the times.



Move to Machine

Plan Machines One Job at a Time

ActionWhat it does
Level Load MachineFor the machine of the selected operation: one job at a time, most urgent first.
Sequence All MachinesThe same for every machine on the board. Operations of an order stay in sequence; days without capacity are skipped; started and frozen work stays.

Note: Operations planned on a work center (not on a machine) cannot move to a machine from the board. Started operations stay on their machine.

Shortages & Order Coverage

A finished product that is not in stock has to come from somewhere. The board tells you, per customer order, where it comes from and whether it is enough.

CoverageBadge on the boardWhat it meansWhat to do
From stocklabel ends in « · from stock »Stock that no other order has taken covers the whole order.Nothing. Ship it.
Supply on time—A production order or purchase covers it and is ready in time.Nothing.
Supply latered outline, +N dIt is covered, but the supply is ready after the shipment date.Expedite, move the supply, or agree a new date.
Partly shortPART SHORTPart of the quantity has no supply at all.Plan the rest, or ship part.
ShortSHORTNothing covers the order.Run planning (or Chain Planning), or make a production order; give the customer a promise date.
Production order misses materialCOMPONENTSA component has no supply, or arrives after the production order needs it.Trace it; expedite the purchase or the component’s production.

Find Them

  • Shortages in the toolbar shows only short customer orders and production orders that miss components.

  • Order Coverage (Board menu) lists every customer order, most urgent first, with coverage, quantity from stock, short quantity and the date it can really ship.



Order Coverage

Promise Dates

When a customer asks “when can I have it?”, the promise date gives an answer you can keep. It never uses stock, supply or machine time that is already given to another order.

How the Date is Worked Out:

  1. Free stock: Stock that no order has taken, now.

  2. Free existing supply: Production orders and purchases already planned, with quantity no order has taken, on their date.

  3. Make or buy the rest: Each component from free stock or supply, or made or bought itself (up to three BOM levels); bought items take their lead time.

  4. Machine hours: Each operation of the routing is fitted into the free hours of its machine, day by day, after everything already on the board.

  5. The last step done, plus the Safety Days in Promise Date, is the earliest shipment date. The step that decides it is marked Bottleneck.

Where to Use It:

FromThen
The board: select a customer order, Promise date…Use as Shipment Date moves the order on the board (what-if); Apply Changes writes it.
A sales order line: Promise Date (Stock and Capacity)Use as Shipment Date writes the date on the line at once.
Tell me: Promise DateEnter any item and quantity, for a quote or a phone call.


Promise Date

Business Scenarios: What the Board Does

The situations a planner meets every week, and what the board does in each. All are what-ifs until Apply Changes.

SituationWhat you doWhat the board does
Customer orders
Customer wants it earlierMove the sales order earlier, Move Supply with Order onIts supply moves too. Red where it would have to start before today: that is how much earlier is possible.
Customer accepts it laterMove the sales order laterSupply can stay (stock ready early) or move with it (frees capacity this week).
Rush order from a key customerExpedite…Stock first, supply earlier, first on the machines; list of orders that gain and wait.
New order, customer asks for a datePromise date…Earliest date from free stock, supply, components and free machine hours.
Finished product not in stockLook at coverageSHORT until planning creates supply; then Supply on time or late.
Production
Production order needs more timeMove it later, Push Dependent Orders on or offOn: everything above moves, up to the customer order. Off: they turn amber and the customer order red.
Machine overloadedSequence All Machines or Level Load MachineOne job at a time, most urgent first; the orders that become late turn red.
Machine down or busyDrag operations to another machine of the work centerDuration follows the new machine; Apply writes the machine on the routing line.
Work already started—Started operations and orders do not move; the rest is planned around them.
Work for the next days is preparedSet a Frozen ZonePush, expedite and sequencing leave frozen work alone; you can still move it yourself.
Material
Supplier is lateMove the purchase laterProduction orders that need it turn amber (COMPONENTS), customer orders red; Push moves them out.
Component missingLook at COMPONENTS / TraceShows which component, how much is short and when it arrives.
Two orders want the same stockSet prioritiesRush and High get it first; the other order turns SHORT or late. Reserved stock stays with its order.